1/5 · Requirements Life Cycle Management · easy
Which of the following is one of the five tasks within the Requirements Life Cycle Management knowledge area in BABOK v3?
APrepare for Elicitation
BMeasure Solution Performance
CTrace Requirements
DDefine Requirements Architecture
Show answer & explanation
C is correct. The five tasks of Requirements Life Cycle Management are: Trace Requirements, Maintain Requirements, Prioritize Requirements, Assess Requirements Changes, and Approve Requirements. The distractors are real BABOK tasks but belong to other knowledge areas.
↗ BABOK v3 — Requirements Life Cycle Management
2/5 · Requirements Life Cycle Management
Which of the following is a typical basis a business analyst uses when prioritizing requirements?
AWhichever requirements were elicited first during the project
BThe number of words used to describe each requirement
CBenefit, penalty, cost, risk, dependencies, time sensitivity, stability, and regulatory or policy compliance
DThe alphabetical order of the requirement identifiers in the repository
Show answer & explanation
C is correct. Prioritize Requirements ranks requirements by relative importance using a defined basis. BABOK v3 identifies bases such as benefit, penalty, cost, risk, dependencies, time sensitivity, stability, and regulatory or policy compliance. These help stakeholders agree on the order in which requirements should be addressed when resources or time are constrained.
↗ BABOK v3 — Requirements Life Cycle Management
3/5 · Requirements Life Cycle Management
A team writes a set of detailed solution requirements that are produced directly from a higher-level stakeholder requirement. The business analyst wants to record that the detailed items came from that higher-level requirement. Which traceability relationship should be used?
ADerive
BSatisfy
CDepends on
DValidate
Show answer & explanation
A is correct. The Derive relationship is used when one requirement is derived or transformed from another, which is common when solution requirements are produced from stakeholder requirements. Satisfy links solution components to requirements, and Validate links requirements to verification artifacts.
↗ BABOK v3 — Requirements Life Cycle Management
4/5 · Requirements Life Cycle Management · hard
Before requesting approval, a business analyst needs to know who is authorized to approve a set of requirements and how disagreements among approvers will be resolved. Where would the BA most appropriately find this information?
AThe solution scope statement
BThe governance approach, which defines decision-making and approval authority
CThe requirements traceability matrix
DThe prioritization criteria list
Show answer & explanation
B is correct. Approve Requirements depends on the governance approach, which specifies who has approval authority, how approvals are obtained, and how conflicts among stakeholders are resolved. Without clear governance, the BA cannot route requirements to the right approvers.
↗ BABOK v3 — Requirements Life Cycle Management
5/5 · Requirements Life Cycle Management · hard
During an approval session, two stakeholder groups cannot agree on whether a set of requirements is acceptable to sign off. To keep the requirements moving toward approval, what is the most appropriate action for the business analyst within the Approve Requirements task?
AFacilitate resolution of the disagreement so the stakeholders can reach a documented agreement
BRemove the disputed requirements from scope without further discussion
CApprove the requirements personally so the schedule is not delayed
DDefer the entire initiative until all stakeholders independently agree on their own
Show answer & explanation
A is correct. The Approve Requirements task is about obtaining agreement on and sign-off of requirements from stakeholders who have the authority and information to approve them. When stakeholders disagree, the business analyst facilitates resolution and consensus-building (often supported by the governance approach) so a documented agreement can be reached. The analyst facilitates approval but does not normally hold approval authority.
↗ BABOK v3 — Requirements Life Cycle Management
Other ECBA® areas
The same kind of free sample for every other section of the ECBA® bank:
Study Requirements Life Cycle Management with instant feedback
6 free questions · filter study mode by area and difficulty · error log with spaced repetition · no card, no dumps, no ads.
Create your free account →
ExamDeck is an independent study tool, not affiliated with IIBA®. ECBA® and BABOK® are trademarks of the International Institute of Business Analysis. Exam facts checked against official IIBA materials (as of August 2026); confirm current details on iiba.org.