ECBA® practice questions: Requirements Life Cycle Management

5 free questions from 47 on this area · answer and explanation for each · no sign-up

These 5 questions come from the Requirements Life Cycle Management section of our ECBA® bank (47 questions on this area). Every question is original, with the correct answer explained and linked to the source it is drawn from.

Try 6 free ECBA® questions → All ECBA® sample questions

Free: 6 questions in study mode, no card. All 47 Requirements Life Cycle Management questions and the full ECBA® bank: $15 one-time.

How this bank fits the current exam. Since 21 July 2025 the ECBA exam is organised in nine domains built around the Business Analysis Core Concept Model. Our questions are filed by the six BABOK knowledge areas instead: IIBA's blueprint ships with a reference map that ties each domain back to the BABOK Guide, so the content is the same, only sliced differently. How the areas map to the nine domains → Source: IIBA exam blueprint and reference map
1/5 · Requirements Life Cycle Management · easy
Which of the following is one of the five tasks within the Requirements Life Cycle Management knowledge area in BABOK v3?
APrepare for Elicitation
BMeasure Solution Performance
CTrace Requirements
DDefine Requirements Architecture
Answer: C. The five tasks of Requirements Life Cycle Management are: Trace Requirements, Maintain Requirements, Prioritize Requirements, Assess Requirements Changes, and Approve Requirements. The distractors are real BABOK tasks but belong to other knowledge areas. Source: BABOK v3 — Requirements Life Cycle Management
2/5 · Requirements Life Cycle Management
Which of the following is a typical basis a business analyst uses when prioritizing requirements?
AElicitation sequence, requester seniority, document length, and the analyst's own personal preference
BWord count, author name, template format, and the date each requirement was last edited
CBenefit, penalty, cost, risk, dependencies, time sensitivity, stability, and regulatory compliance
DAlphabetical identifier order, repository folder, page number, and the tool used to store them
Answer: C. Prioritize Requirements ranks requirements by relative importance using a defined basis. BABOK v3 identifies bases such as benefit, penalty, cost, risk, dependencies, time sensitivity, stability, and regulatory or policy compliance. These help stakeholders agree on the order in which requirements should be addressed when resources or time are constrained. Source: BABOK v3 — Requirements Life Cycle Management
3/5 · Requirements Life Cycle Management
A team writes a set of detailed solution requirements that are produced directly from a higher-level stakeholder requirement. The business analyst wants to record that the detailed items came from that higher-level requirement. Which traceability relationship should be used?
ADerive
BSatisfy
CDepends on
DValidate
Answer: A. The Derive relationship is used when one requirement is derived or transformed from another, which is common when solution requirements are produced from stakeholder requirements. Satisfy links solution components to requirements, and Validate links requirements to verification artifacts. Source: BABOK v3 — Requirements Life Cycle Management
4/5 · Requirements Life Cycle Management · hard
Before requesting approval, a business analyst needs to know who is authorized to approve a set of requirements and how disagreements among approvers will be resolved. Where would the BA most appropriately find this information?
AThe solution scope statement, which defines the boundaries of the solution
BThe governance approach, which defines decision-making and approval authority
CThe requirements traceability matrix, which links requirements to their sources
DThe prioritization criteria list, which defines how requirements are ranked before approval
Answer: B. Approve Requirements depends on the governance approach, which specifies who has approval authority, how approvals are obtained, and how conflicts among stakeholders are resolved. Without clear governance, the BA cannot route requirements to the right approvers. Source: BABOK v3 — Requirements Life Cycle Management
5/5 · Requirements Life Cycle Management · hard
During an approval session, two stakeholder groups cannot agree on whether a set of requirements is acceptable to sign off. To keep the requirements moving toward approval, what is the most appropriate action for the business analyst within the Approve Requirements task?
AFacilitate resolution of the disagreement so the stakeholders can reach a documented agreement
BRemove the disputed requirements from scope without further discussion
CApprove the requirements personally so the schedule is not delayed
DDefer the entire initiative until all stakeholders independently agree on their own
Answer: A. The Approve Requirements task is about obtaining agreement on and sign-off of requirements from stakeholders who have the authority and information to approve them. When stakeholders disagree, the business analyst facilitates resolution and consensus-building (often supported by the governance approach) so a documented agreement can be reached. The analyst facilitates approval but does not normally hold approval authority. Source: BABOK v3 — Requirements Life Cycle Management
Try 6 more free ECBA® questions → See the whole ECBA® bank

Other ECBA® areas

The same kind of free sample for every other section of the ECBA® bank:

Business Analysis Planning and Monitoring46 qElicitation and Collaboration47 qStrategy Analysis47 qRequirements Analysis and Design Definition47 qSolution Evaluation47 q

Practise ECBA® with instant feedback

6 free questions in study mode · no card · full ECBA® bank with area filters and the error log: $15 one-time · no dumps, no ads.

Start ECBA® free →
Read next
ECBA Study Plan: 30 to 60 Hours to a First IIBA Credential, Week by Week ECBA is now 50 situation-based questions in 75 minutes across nine domains, with no eligibility hours. A four-week self-study plan. Verified 20 Sep 2026. ECBA vs CCBA vs CBAP: Which IIBA Certification Fits Your Experience Level? (2026) ECBA, CCBA or CBAP? The eligibility gate that picks for you, what the 2026 ECBA rewrite changed, and each credential's three-year cost, verified against IIBA.
ExamDeck is an independent study tool, not affiliated with IIBA®. ECBA® and BABOK® are trademarks of the International Institute of Business Analysis. Exam facts checked against official IIBA materials (as of October 2026); confirm current details on iiba.org.