1/5 · Managing the Test Activities · easy
A test team defines a set of conditions that must be satisfied before a given test level, such as system testing, is authorized to begin. What are these conditions called in the ISTQB CTFL syllabus?
AResumption criteria
BExit criteria
CSuspension criteria
DEntry criteria
Show answer & explanation
D is correct. Entry criteria specify the preconditions for undertaking a given test activity, such as availability of testable code, a stable test environment, and completed test data. They complement exit criteria, which define completion of the same activity.
↗ ISTQB CTFL Syllabus v4.0.1 — Managing the Test Activities
2/5 · Managing the Test Activities
With limited time before a release, a test team decides to execute the test cases covering the checkout and payment features first, because a failure in those areas would have severe business and financial consequences, even though the search feature is used more frequently day-to-day. On what basis is the team prioritizing its test cases?
ARequirements-based prioritization sorted purely by the order requirements appear in the specification document.
BCoverage-based prioritization, aiming to exercise as many different code paths as early as possible.
CRandom prioritization intended to remove any bias from the selection of test cases.
DRisk-based prioritization, running the test cases that address the areas of highest risk to the business first.
Show answer & explanation
D is correct. Risk-based test case prioritization runs the test cases addressing the highest-risk areas of the product first, so that if testing is cut short, the most critical functionality has already been verified.
↗ ISTQB CTFL Syllabus v4.0.1 — Managing the Test Activities
3/5 · Managing the Test Activities
During test execution, a test manager tracks the percentage of planned test cases executed, the percentage passed and failed, the percentage of identified risks covered by executed tests, and defect density per module. Collecting these measures primarily supports which test management activity?
ATest estimation, to predict the overall project budget before any testing has started.
BTest monitoring, to compare actual progress against the test plan and provide a basis for test control decisions.
CRequirements elicitation, to determine stakeholder needs for the next product release.
DConfiguration management, to track versions and changes of the test items and testware under test.
Show answer & explanation
B is correct. Metrics such as percentage of test cases executed/passed, risk or requirements coverage achieved, and defect density are collected during test monitoring to compare actual progress to the test plan and to support test control decisions.
↗ ISTQB CTFL Syllabus v4.0.1 — Managing the Test Activities
4/5 · Managing the Test Activities
A test team defines that system testing may only start once the test environment is available, the required test data has been prepared, and the code under test has passed a smoke test. According to the ISTQB CTFL Syllabus, this set of conditions is an example of:
AEntry criteria
BA defect report
CA risk level
DExit criteria
Show answer & explanation
A is correct. Entry criteria define the preconditions that must be satisfied before a test activity, such as a test level, can begin, such as environment readiness, test data availability, and a passing smoke test. Exit criteria, by contrast, define when a test activity can be considered complete; defect reports document individual defects; and risk level is derived from likelihood and impact, unrelated to start-of-testing preconditions.
↗ ISTQB CTFL Syllabus v4.0.1 — Managing the Test Activities
5/5 · Managing the Test Activities
An organization creates a single, high-level document describing the general test levels to be performed (e.g., component, integration, system, acceptance) and generic entry/exit criteria applicable across all of its projects, independent of any one project's specific context. According to the CTFL v4.0 syllabus, which term best describes this document?
ATest policy
B(Project-specific) test plan
CTest approach
DTest strategy
Show answer & explanation
D is correct. CTFL v4.0 distinguishes a test strategy (generic, organization-wide description of test levels and criteria) from a test approach (its project-specific tailoring) and from a test policy (even higher-level statement of testing philosophy without concrete process detail). Confusing these related terms is a common source of error since they overlap colloquially.
↗ the ISTQB Certified Tester Foundation Level (CTFL) Syllabus v4.0 — Managing the Test Activities
Practise all 29 Managing the Test Activities questions - start free → See the whole CTFL v4.0 bank

Other CTFL v4.0 areas

The same kind of free sample for every other section of the CTFL v4.0 bank:

Fundamentals of Testing29 qTesting Throughout the Software Development Lifecycle23 qStatic Testing16 qTest Analysis and Design36 qTest Tools12 q

Study Managing the Test Activities with instant feedback

6 free questions · filter study mode by area and difficulty · error log with spaced repetition · no card, no dumps, no ads.

Create your free account →
Read next
CTFL (ISTQB) Study Plan: 4 Weeks to Pass Without a Bootcamp ISTQB CTFL: 40 questions, 60 minutes, 26 to pass, no course required. A four-week self-study plan sized to the syllabus hours. Verified 14 Sep 2026.
ExamDeck is an independent study tool, not affiliated with, endorsed by, or sponsored by ISTQB. CTFL v4.0 and related marks are trademarks of their respective owners, used for identification only. Exam facts checked against official ISTQB materials (as of September 2026); always confirm current details with the vendor before booking.