1/5 · The PRINCE2 processes · easy
A project mandate has just been received from corporate management. The newly appointed Executive instructs the Project Manager to produce a fully costed, detailed Business Case—including NPV and full benefits quantification—before the project is even authorized to move into initiation. Is this instruction appropriate for the 'Starting up a project' process?
ANo — only an outline Business Case is required during starting up a project; the detailed, quantified Business Case is developed later, during initiating a project.
BYes — a fully detailed Business Case with NPV must always be completed before initiation can be authorized.
CYes, but only if the project is being directly managed by an external supplier rather than the customer organization.
DNo — starting up a project does not require any Business Case content at all; it is added only when closing the project.
Show answer & explanation
A is correct. Starting up a project produces an outline Business Case sufficient to justify initiating the project; the detailed, fully quantified Business Case with costs, benefits and investment appraisal is developed as part of the PID during Initiating a project and confirmed before the Project Board authorizes the project.
↗ the official PRINCE2 7 Practitioner syllabus + 'Managing Successful Projects with PRINCE2, 7th Edition' (PeopleCert, 2023) — The PRINCE2 processes
2/5 · The PRINCE2 processes
At project closure, the Project Manager notes that several key benefits are not expected to materialize until 18 months after the project ends. Because the project team will have disbanded by then, the Project Manager omits these benefits from the Benefits Review Plan, planning to report only benefits already achieved. Is this appropriate?
ANo — instead of updating the Benefits Review Plan, the project should be kept open until all benefits are realized, however long that takes.
BYes — measuring post-project benefits is the sole responsibility of the Senior User as an individual, so it does not need to appear in any project document.
CYes — PRINCE2 only requires benefits realized during the project lifecycle to be documented; post-project benefits fall outside the method's scope.
DNo — the Benefits Review Plan must be updated at closure to include arrangements for measuring all benefits, including those due after the project ends, with ownership handed to corporate/programme management or the operational area.
Show answer & explanation
D is correct. Because many benefits are only realizable after a project's products are in operational use, the Benefits Review Plan is created early and updated at closure to schedule post-project reviews, with responsibility explicitly transferred to corporate/programme management or business-as-usual owners.
↗ the official PRINCE2 7 Practitioner syllabus + 'Managing Successful Projects with PRINCE2, 7th Edition' (PeopleCert, 2023) — The PRINCE2 processes
3/5 · The PRINCE2 processes · hard
A project has three management stages. As the final (third) delivery stage nears its end, the Project Manager runs a full 'Managing a stage boundary' process, producing a plan and tolerances for a fourth stage for the Project Board to authorize, intending to hand over products afterward. Is this the correct process to apply?
ANo — Managing a stage boundary should never be used in a project with only three stages; it applies only to projects with four or more stages.
BYes — Managing a stage boundary must always be performed at the end of every stage, including the last, before Closing a project can begin.
CNo — because this is the project's final stage, there is no next stage to plan; the Project Manager should instead move into Closing a project to confirm handover, evaluate the project, and prepare closure recommendations.
DYes, and in addition the Project Board must independently repeat the full Initiating a project process before the project can close.
Show answer & explanation
C is correct. PRINCE2's Managing a Stage Boundary process is used at the end of each stage except the last one. At the end of the final stage, the project transitions directly into Closing a Project rather than planning a further stage, since there is no next stage to authorize.
↗ the official PRINCE2 7 Practitioner syllabus + 'Managing Successful Projects with PRINCE2, 7th Edition' (PeopleCert, 2023) — The PRINCE2 processes
4/5 · The PRINCE2 processes · hard
The Project Manager has escalated an exception report showing that a delivery stage will overrun its agreed cost tolerance due to unforeseen currency fluctuations. After reviewing options, the Project Board decides the project should continue and asks for a revised plan covering the remainder of the current stage before work resumes. Which process activity should produce this plan, and who requests it?
AThe Project Manager produces the plan unilaterally under controlling a stage, since they are already managing the stage day to day.
BCorporate or programme management produces the plan, since the currency risk originates outside the project's control.
CThe Team Manager produces a revised work package plan under managing product delivery, since they are closest to the currency-affected costs.
DThe Project Board requests it, and the Project Manager produces an exception plan under the managing a stage boundary process to replace the remainder of the current stage.
Show answer & explanation
D is correct. Produce an exception plan is a managing a stage boundary activity used when the Project Board, having reviewed an escalated exception report, decides the project should continue and asks the Project Manager for a revised plan to replace the remainder of the affected stage.
↗ the official PRINCE2 7 Practitioner syllabus + 'Managing Successful Projects with PRINCE2, 7th Edition' (PeopleCert, 2023) — The PRINCE2 processes
5/5 · The PRINCE2 processes
As the final delivery stage of a project nears completion, the Project Manager begins preparing to plan the next stage and update the project plan, following the same pattern used at previous stage boundaries. Is this the correct process to apply at this point?
AYes, but the Project Manager should also run closing a project activities in parallel throughout the final stage.
BNo, but only because the Project Board must first decide which of the two processes applies on a case-by-case basis.
CYes; managing a stage boundary is used at every stage boundary, including the final one, in exactly the same way.
DNo; for the final stage, closing a project is used instead of managing a stage boundary, since there is no next stage to plan and the focus shifts to evaluation, handover, and closure recommendation.
Show answer & explanation
D is correct. PRINCE2 uses managing a stage boundary between stages when a further stage will follow, producing a next stage plan and updated project plan. At the end of the final stage there is no next stage, so the Project Manager instead moves into closing a project, which handles evaluation, handover, and recommending closure.
↗ the official PRINCE2 7 Practitioner syllabus + 'Managing Successful Projects with PRINCE2, 7th Edition' (PeopleCert, 2023) — The PRINCE2 processes
Practise all 35 The PRINCE2 processes questions - start free → See the whole PRINCE2 7 Pract. bank

Other PRINCE2 7 Pract. areas

The same kind of free sample for every other section of the PRINCE2 7 Pract. bank:

The PRINCE2 principles16 qPeople management14 qBusiness Case practice12 qOrganizing practice13 qPlans practice13 qQuality practice12 qRisk practice12 qIssues practice12 qProgress practice10 q

Study The PRINCE2 processes with instant feedback

6 free questions · filter study mode by area and difficulty · error log with spaced repetition · no card, no dumps, no ads.

Create your free account →
Read next
PRINCE2 Foundation vs Practitioner: What Changes, What It Costs, Who Needs Which PRINCE2 Foundation (60 questions, closed book) vs Practitioner (scenarios, open book), both at 60% to pass. What each bundle costs and who needs which.
ExamDeck is an independent study tool, not affiliated with, endorsed by, or sponsored by PeopleCert. PRINCE2 7 Pract. and related marks are trademarks of their respective owners, used for identification only. Exam facts checked against official PeopleCert materials (as of September 2026); always confirm current details with the vendor before booking.