PSPO II · Scrum.org · Stakeholder and Customer Engagement · Bank updated 2026-09-12
PSPO II practice questions: Stakeholder and Customer Engagement
5 free questions from 15 on this area · answer and explanation for each · no sign-up
These 5 questions come from the Stakeholder and Customer Engagement section of our PSPO II bank (15 questions on this area, which carries 15% of the real exam). Every question is original, with the correct answer explained and linked to the source it is drawn from.
1/5 · Stakeholder and Customer Engagement · easy
A senior VP repeatedly asks for private, ad hoc demos before every Sprint Review, bypassing the rest of the Scrum Team and stakeholders, so she can be 'first to know.' Which response is most consistent with the Scrum Guide (2020)?
ADelegate the private demos to a Developer so the Product Owner can stay focused on Product Backlog refinement.
BDecline any contact with her outside formal Scrum events, since only the Product Owner is permitted to speak with stakeholders in Scrum.
CExplain that the Sprint Review is the collaborative event where the Scrum Team and stakeholders inspect the Increment together, invite her to attend and engage there, and offer another channel for general Product Goal updates if needed.
DAgree to the private demo, since keeping a powerful stakeholder satisfied protects the roadmap's political support.
Show answer & explanation
2/5 · Stakeholder and Customer Engagement
A key enterprise customer demands a written commitment to exactly twelve named features by a fixed date six months out, threatening to cancel the contract otherwise. Which response best aligns with Scrum's empirical approach?
ASign the commitment as written, since large contracts require certainty, and direct the team to work overtime to guarantee the date.
BHand the negotiation entirely to the Scrum Master, since managing stakeholder conflict is a Scrum Master accountability rather than the Product Owner's.
CShare the current empirical forecast based on team performance data, negotiate around the Product Goal, offer a forecast range for the highest-value items, and agree to revisit progress each Sprint so scope can adapt to new evidence.
DRefuse to discuss any timelines at all, since Scrum prohibits date-based commitments and only the Sprint is a valid unit of planning.
Show answer & explanation
3/5 · Stakeholder and Customer Engagement · hard
Mid-Sprint, the Product Owner is running customer discovery interviews in parallel with the Development Team's work toward the current Sprint Goal (a checkout redesign). Early, limited signals suggest the current approach may not be optimal, but the evidence is not yet conclusive, and stakeholders expect the increment on schedule. What is the most appropriate action?
AImmediately redirect the Development Team mid-Sprint to the new approach, since customer evidence should always override an existing Sprint plan.
BAsk the Scrum Master to decide whether to change direction, since the Scrum Master is accountable for the effectiveness of the Scrum Team's practices.
CLet the current Sprint continue toward its Sprint Goal, continue discovery in parallel, and use the resulting evidence to inform the ordering and content of future Product Backlog items and Sprint Goals.
DIgnore the discovery findings entirely until the whole release finishes, so the Development Team's plan and stakeholder expectations remain undisturbed.
Show answer & explanation
4/5 · Stakeholder and Customer Engagement · hard
Two Scrum Teams share ownership of a single product used by both an internal operations business unit and an external customer segment. The operations leader insists their requests must always rank first because they 'fund the team,' while customer segment leads argue external revenue should always dominate. As the sole Product Owner for this product, what is the most defensible approach under Scrum?
AMaintain two separate Product Backlogs, one per business unit, each with Product Owner authority delegated to the respective unit leader.
BGive standing priority to whichever unit generates more direct revenue, since Current Value is defined strictly by revenue figures alone.
CAlternate ordering between the two units' requests every other Sprint so influence remains balanced regardless of expected value.
DMaintain a single ordered Product Backlog, order items by expected overall value toward the Product Goal using available evidence (such as expected impact on Current Value, Unrealized Value, and Time-to-Market), and transparently explain the rationale to both groups rather than granting either standing priority.
Show answer & explanation
5/5 · Stakeholder and Customer Engagement
Midway through a Sprint, market conditions shift dramatically and the Sprint Goal becomes clearly obsolete; a major customer is demanding an entirely different feature set start immediately. What is the Scrum-consistent path forward?
AThe Product Owner has the authority to cancel the Sprint because the Sprint Goal is obsolete, then works with the Scrum Team to plan a new Sprint with a Sprint Goal reflecting updated priorities.
BThe Scrum Master should cancel the Sprint, since they own the Scrum process and its events.
CThe Developers should unilaterally abandon the current Sprint Backlog and start the customer's new request without formally ending the Sprint.
DThe Scrum Team must complete the current Sprint regardless of the obsolete Sprint Goal, since only a Sprint's natural end can trigger replanning.
Show answer & explanation
Other PSPO II areas
The same kind of free sample for every other section of the PSPO II bank:
Study Stakeholder and Customer Engagement with instant feedback
6 free questions · filter study mode by area and difficulty · error log with spaced repetition · no card, no dumps, no ads.
Create your free account →
ExamDeck is an independent study tool, not affiliated with, endorsed by, or sponsored by Scrum.org. PSPO II and related marks are trademarks of their respective owners, used for identification only. Exam facts checked against official Scrum.org materials (as of August 2026); always confirm current details with the vendor before booking.