1/5 · Executing the PI
During the risk review portion of PI Planning, a risk is raised: Team A depends on an API from Team B that may not be ready until the IP Iteration. Team B agrees on the spot to resequence its backlog and move the API story into Iteration 1, fully addressing the timing concern before Team A needs it. How should this risk be categorized using ROAM?
AResolved
BMitigated
CAccepted
DOwned
Show answer & explanation
2/5 · Executing the PI · hard
Team Delta finishes PI Planning with two PI objectives marked as 'uncommitted' because of significant, unresolved dependency risk on an external vendor deliverable. As RTE, how should this be handled going into ART execution?
ATreat them as committed anyway since the team still intends to attempt the work
BRemove the objectives from the plan and backlog entirely since the team cannot commit to them
CUse the uncommitted status to reduce the team's velocity baseline for the next PI as a corrective measure
DDocument the uncommitted objectives and communicate them transparently to Business Owners and stakeholders as no-guarantee items; the team still plans and tracks progress on them, but they carry no formal delivery commitment
Show answer & explanation
3/5 · Executing the PI · hard
The RTE observes that too many Features are being pulled into the 'Analyzing' state of the Program Kanban simultaneously, causing Product Management to context-switch heavily and delaying refinement for the whole ART. What action reflects proper application of Kanban principles at the ART level?
AEscalate to Lean Portfolio Management to have the Portfolio Kanban override and take control of all Program-level Feature refinement
BRemove WIP limits entirely since the Program Kanban should allow unlimited Features to be analyzed in parallel
CAdd all pending Features into the current PI plan immediately regardless of capacity, to avoid delaying customers
DEstablish and enforce a WIP limit on the Program Kanban's Analyzing state so only a manageable number of Features are analyzed at once, pulling new ones only as capacity frees up
Show answer & explanation
4/5 · Executing the PI · easy
How often does the System Demo occur during PI execution?
ADaily, as part of each team's Daily Stand-up.
BOnly during the Innovation and Planning (IP) Iteration.
CAt the end of every iteration, giving stakeholders an integrated view of new Features delivered by all teams on the ART.
DOnly once, at the very end of the PI, replacing the need for any earlier demos.
Show answer & explanation
5/5 · Executing the PI · easy
What is the PRIMARY purpose of the Innovation and Planning (IP) Iteration within a Program Increment?
ATo serve as a hardening or stabilization sprint where all remaining defects from the PI must be fixed before release.
BTo give teams an extra iteration of feature development capacity that is excluded from velocity calculations.
CTo provide dedicated time for innovation, continuing education, PI Planning, and Inspect & Adapt, while also acting as an estimating guard band for the PI.
DTo allow the RTE to conduct individual performance reviews for every team member.
Show answer & explanation
Other SAFe RTE areas
The same kind of free sample for every other section of the SAFe RTE bank:
Study Executing the PI with instant feedback
6 free questions · filter study mode by area and difficulty · error log with spaced repetition · no card, no dumps, no ads.
Create your free account →
ExamDeck is an independent study tool, not affiliated with, endorsed by, or sponsored by Scaled Agile. SAFe RTE and related marks are trademarks of their respective owners, used for identification only. Exam facts checked against official Scaled Agile materials (as of August 2026); always confirm current details with the vendor before booking.