1/5 · The ADM · easy
In the TOGAF ADM cycle diagram, which activity sits at the center (hub) of the cycle and interacts continuously with every surrounding phase?
ARequirements Management
BArchitecture Vision
CArchitecture Change Management
DPreliminary Phase
Show answer & explanation
A is correct. Requirements Management is not a sequential phase but a continuous process shown at the center of the ADM diagram, ensuring architecture requirements identified in any phase are captured and fed to/from all relevant phases throughout the cycle.
↗ the TOGAF Standard, 10th Edition + The Open Group X2202 Conformance Requirements (Level 1 Syllabus) — The ADM
2/5 · The ADM
Phase C of the ADM addresses which two architecture domains, typically as sub-phases or separate iterations?
ABusiness Architecture and Technology Architecture
BData Architecture and Application Architecture
CApplication Architecture and Business Architecture
DData Architecture and Technology Architecture
Show answer & explanation
B is correct. Phase C, Information Systems Architectures, is generally split into Data Architecture and Application Architecture sub-phases, developing Target Architectures for how data and applications will support the business.
↗ the TOGAF Standard, 10th Edition + The Open Group X2202 Conformance Requirements (Level 1 Syllabus) — The ADM
3/5 · The ADM · hard
The Architecture Vision produced in Phase A is refined into detailed Target Architectures in Phases B, C, and D, and the resulting gap analyses feed into Phase E's roadmap work. This describes which characteristic of the ADM?
AThe replacement of business requirements with technical constraints as the cycle progresses
BThe requirement to complete all phases in a single pass with no iteration
CThe separation of governance from architecture development
DThe flow of architecture information between ADM phases, where the outputs of one phase become inputs to subsequent phases
Show answer & explanation
D is correct. The ADM phases are interconnected: each phase consumes inputs, including outputs from earlier phases, and produces outputs/deliverables that feed forward into later phases, ensuring traceability from vision through governance.
↗ the TOGAF Standard, 10th Edition + The Open Group X2202 Conformance Requirements (Level 1 Syllabus) — The ADM
4/5 · The ADM
What is the purpose of Phase D: Technology Architecture within the ADM?
ATo ensure that implementation projects conform to the defined architecture
BTo manage architecture requirements as they arise throughout the ADM cycle
CTo evaluate and select among alternative implementation approaches based on trade-offs such as cost and risk
DTo develop the Target Technology Architecture that enables the logical and physical application and data components and the Architecture Vision, addressing the Statement of Architecture Work
Show answer & explanation
D is correct. Phase D develops the Target Technology Architecture, providing the infrastructure needed to support the Data and Application Architectures defined in Phase C, aligned with the Architecture Vision and Statement of Architecture Work.
↗ the TOGAF Standard, 10th Edition + The Open Group X2202 Conformance Requirements (Level 1 Syllabus) — The ADM
5/5 · The ADM · hard
An architecture team has produced an updated version of the Architecture Definition Document during Phase C, capturing the Target Data and Application Architectures. The document has not yet been reviewed by the Architecture Board or formally signed off by stakeholders. Which best describes this deliverable's status under TOGAF's distinction between draft and approved work products?
AIt automatically becomes an Approved deliverable once it is checked into the Architecture Repository
BIt is an Approved deliverable, because it was produced by the accountable architecture team and therefore needs no governance review
CIt is neither Draft nor Approved, because the Architecture Definition Document is only ever finalized once, at the very end of Phase H
DIt is a Draft deliverable, since it has not yet passed through architecture governance review and stakeholder sign-off
Show answer & explanation
D is correct. Deliverables such as the Architecture Definition Document are typically produced and refined as Draft outputs across successive phases and only attain Approved status once reviewed and formally signed off through the enterprise's architecture governance, such as the Architecture Board.
↗ the TOGAF Standard, 10th Edition + The Open Group X2202 Conformance Requirements (Level 1 Syllabus) — The ADM
Practise all 33 The ADM questions - start free → See the whole TOGAF EA Found. bank

Other TOGAF EA Found. areas

The same kind of free sample for every other section of the TOGAF EA Found. bank:

Concepts19 qDefinitions11 qADM Techniques13 qApplying the ADM9 qArchitecture Governance8 qArchitecture Content11 qTOGAF Certification Program3 q

Study The ADM with instant feedback

6 free questions · filter study mode by area and difficulty · error log with spaced repetition · no card, no dumps, no ads.

Create your free account →
Read next
TOGAF Certification in 2026: Cost, Format, and Whether Architects Still Need It TOGAF EA Foundation: 40 closed-book questions, 60 minutes, 24 to pass, USD 405 or 435 by channel. The combined-exam trap and registry numbers, checked 16 Sep.
ExamDeck is an independent study tool, not affiliated with, endorsed by, or sponsored by The Open Group. TOGAF EA Found. and related marks are trademarks of their respective owners, used for identification only. Exam facts checked against official The Open Group materials (as of September 2026); always confirm current details with the vendor before booking.