AgileBA Found. practice questions: Agile Business Case, Estimating and Benefits

5 free questions from 25 on this area · answer and explanation for each · no sign-up

These 5 questions come from the Agile Business Case, Estimating and Benefits section of our AgileBA Found. bank (25 questions on this area, which carries 15% of the real exam). Every question is original, with the correct answer explained and linked to the source it is drawn from.

Start 6 free in study mode → All AgileBA Found. sample questions
1/5 · Agile Business Case, Estimating and Benefits · easy
Which DSDM role is ultimately accountable for the Business Case, including confirming that adequate funding and justification exist for the project to proceed?
ATechnical Coordinator
BBusiness Ambassador
CBusiness Sponsor
DBusiness Visionary
Show answer & explanation
C is correct. The Business Sponsor is the most senior business role on a DSDM project and holds ultimate accountability for the Business Case, ensuring sufficient priority, funding and resources exist and that the project remains viable throughout its life.
↗ the AgileBA Handbook (Agile Business Consortium, 2023 edition) + the APMG AgileBA Foundation syllabus — Agile Business Case, Estimating and Benefits
2/5 · Agile Business Case, Estimating and Benefits
Two days before the end of a timebox, the Solution Development Team realises it cannot finish everything originally planned to the agreed level of quality. What should the team do, consistent with DSDM's approach to controlling delivery?
AReduce what is delivered by dropping lower-priority Should Have or Could Have requirements, while still delivering the Must Haves to the agreed quality.
BExtend the timebox deadline to allow all originally planned requirements to be completed, since scope is fixed in DSDM.
CEscalate immediately to bring in extra developers so the original full scope can still be met within the unchanged timebox.
DLower the agreed quality criteria for the Must Have requirements so that all originally planned work can still be finished on time.
Show answer & explanation
A is correct. DSDM fixes time, cost and quality, and flexes scope using MoSCoW. When a timebox is threatened, the team should descope lower-priority Should Have or Could Have requirements while still delivering the Must Haves to the previously agreed quality level, protecting the deadline without compromising quality.
↗ the AgileBA Handbook (Agile Business Consortium, 2023 edition) + the APMG AgileBA Foundation syllabus — Agile Business Case, Estimating and Benefits
3/5 · Agile Business Case, Estimating and Benefits
Within the DSDM Solution Development Team, which role is primarily responsible for day-to-day testing of the evolving solution against agreed acceptance criteria throughout each timebox?
ASolution Tester
BBusiness Sponsor
CBusiness Analyst
DDSDM Coach
Show answer & explanation
A is correct. The Solution Tester works within the Solution Development Team to ensure the solution is tested continuously and to a suitable level of quality throughout each timebox, in line with the acceptance criteria agreed with the business.
↗ the AgileBA Handbook (Agile Business Consortium, 2023 edition) + the APMG AgileBA Foundation syllabus — Agile Business Case, Estimating and Benefits
4/5 · Agile Business Case, Estimating and Benefits · easy
Who bears ultimate accountability for the continued viability of the Business Case throughout a DSDM project, including ensuring adequate funding remains available?
AThe Business Analyst
BThe Business Visionary
CThe Technical Coordinator
DThe Business Sponsor
Show answer & explanation
D is correct. In DSDM/AgileBA the Business Sponsor is the most senior business role on a project and holds ultimate ownership of the Business Case, ensuring it stays valid and adequately funded throughout the lifecycle. Other roles interact with or support the Business Case but do not carry this ultimate accountability, which matters for clarifying escalation when viability is in doubt.
↗ the AgileBA Handbook (Agile Business Consortium / APMG) — Agile Business Case, Estimating and Benefits
5/5 · Agile Business Case, Estimating and Benefits · hard
A solution has just gone live at the end of a DSDM project's Deployment stage. The delivery team reports to the Business Sponsor that 'all the benefits identified in the Business Case have now been achieved,' pointing to the fact that every Must Have requirement was delivered and accepted by users. Which statement best reflects how the AgileBA Handbook would treat this claim?
AThe claim cannot be evaluated at all, because DSDM projects have no mechanism for tracking whether benefits are eventually realised once the project closes.
BThe claim is premature: delivering the solution provides the enabler for the intended benefits, but actual benefit realisation is measured afterwards, as the business adopts and uses the solution in live operation, in line with the Benefits Management Strategy.
CThe claim is accurate, because in DSDM, delivering and accepting all Must Have requirements is by definition equivalent to fully realising every benefit in the Business Case.
DThe claim is premature only because Should Have and Could Have requirements were not necessarily delivered; once all requirements of every priority are delivered, benefits are automatically realised.
Show answer & explanation
B is correct. The Agile Business Case distinguishes a delivered solution (a benefit enabler) from the benefits themselves, which are realised only once the business starts using the solution in live operation. This is why a Benefits Management Strategy, and often a nominated benefit owner, is needed to track realisation after Deployment, rather than assuming delivery of requirements equals realised benefit.
↗ the AgileBA Handbook (Agile Business Consortium / APMG) — Agile Business Case, Estimating and Benefits
Practise all 25 Agile Business Case, Estimating and Benefits questions - start free → See the whole AgileBA Found. bank

Other AgileBA Found. areas

The same kind of free sample for every other section of the AgileBA Found. bank:

Agile Fundamentals and the Agile BA Role35 qRequirements, User Stories and Modelling35 qPrioritization and Timeboxing25 qRoles, Responsibilities and Stakeholders30 q

Study Agile Business Case, Estimating and Benefits with instant feedback

6 free questions · filter study mode by area and difficulty · error log with spaced repetition · no card, no dumps, no ads.

Create your free account →
Read next
ECBA vs CCBA vs CBAP: Which IIBA Certification Fits Your Experience Level? (2026) ECBA, CCBA or CBAP? The eligibility gate that picks for you, what the 2026 ECBA rewrite changed, and each credential's three-year cost, verified against IIBA. PMI-PBA vs CBAP: The Business Analysis Certification Decision, Settled with Data PMI-PBA ($405-555, 36 months of experience) vs CBAP ($495-650 all-in, 7,500 hours plus references): eligibility, exam mechanics, three-year cost, salary data.
ExamDeck is an independent study tool, not affiliated with, endorsed by, or sponsored by APMG. AgileBA Found. and related marks are trademarks of their respective owners, used for identification only. Exam facts checked against official APMG materials (as of August 2026); always confirm current details with the vendor before booking.