AgileBA Found. practice questions: Prioritization and Timeboxing

5 free questions from 25 on this area · answer and explanation for each · no sign-up

These 5 questions come from the Prioritization and Timeboxing section of our AgileBA Found. bank (25 questions on this area, which carries 15% of the real exam). Every question is original, with the correct answer explained and linked to the source it is drawn from.

Start 6 free in study mode → All AgileBA Found. sample questions
1/5 · Prioritization and Timeboxing · easy
Which of the following correctly lists, in order, the five stages that make up the structure of a DSDM timebox?
AInvestigation, Kick-off, Consolidation, Refinement, Close-out
BPlanning, Sprint, Review, Retrospective, Release
CKick-off, Investigation, Refinement, Consolidation, Close-out
DKick-off, Refinement, Investigation, Close-out, Consolidation
Show answer & explanation
C is correct. A DSDM timebox follows five defined stages in sequence: Kick-off (confirm objectives and priorities), Investigation (understand requirements in depth), Refinement (iterative build and test), Consolidation (ensure readiness against acceptance criteria) and Close-out (formal review and sign-off).
↗ the AgileBA Handbook (Agile Business Consortium, 2023 edition) + the APMG AgileBA Foundation syllabus — Prioritization and Timeboxing
2/5 · Prioritization and Timeboxing
What is the primary purpose of the Kick-off stage at the start of a DSDM timebox?
ATo carry out the bulk of the iterative build and testing work on the solution.
BTo confirm the deliverable meets acceptance criteria and is ready to be presented for review.
CTo formally review the completed deliverable with business roles and obtain sign-off.
DTo confirm the objectives, scope and priorities for the timebox and ensure the team understands what is required and has the resources needed to deliver it.
Show answer & explanation
D is correct. Kick-off is a brief opening session in which the team confirms the objectives, scope and MoSCoW priorities for the timebox, ensuring everyone understands the work ahead and that the necessary people and resources are in place before Investigation begins.
↗ the AgileBA Handbook (Agile Business Consortium, 2023 edition) + the APMG AgileBA Foundation syllabus — Prioritization and Timeboxing
3/5 · Prioritization and Timeboxing · hard
During a project, a conflict arises over the relative priority of two Should Have requirements that the Business Ambassador is unable to resolve at the team level. Which DSDM role is primarily responsible for making the final decision on priority in this situation, given their authority to ensure the solution meets the overall business vision?
ATechnical Coordinator
BDSDM Coach
CBusiness Ambassador
DBusiness Visionary
Show answer & explanation
D is correct. The Business Ambassador handles day-to-day business decisions with the team, but priority conflicts that cannot be resolved at that level are escalated to the Business Visionary, who holds the authority to make such decisions and ensure alignment with the overall business vision.
↗ the AgileBA Handbook (Agile Business Consortium, 2023 edition) + the APMG AgileBA Foundation syllabus — Prioritization and Timeboxing
4/5 · Prioritization and Timeboxing · easy
Within MoSCoW prioritisation, a team is debating whether a login requirement should be classed as a Must Have or a Should Have. Which statement correctly reflects how the Handbook distinguishes these two categories?
AA Must Have takes more development effort to build than a Should Have, which is why it is prioritised higher.
BA Must Have must be delivered in the very first timebox of the project, whereas a Should Have may be scheduled into any later timebox.
CWithout the Must Have, the solution is not viable by the agreed delivery date; without the Should Have, a workaround exists so the solution stays viable, even though its absence may be painful.
DA Must Have is any requirement raised by the Business Sponsor, while a Should Have is any requirement raised by end users.
Show answer & explanation
C is correct. The Handbook defines a Must Have as part of the minimum usable subset without which the delivered solution has no viable business value, while a Should Have is important but its omission can be mitigated by a workaround so the solution remains viable. Neither category is determined by effort, by who raised the requirement, or by which timebox it is scheduled into.
↗ the AgileBA Handbook (Agile Business Consortium / APMG) — Prioritization and Timeboxing
5/5 · Prioritization and Timeboxing
Which sequence of stages correctly describes the structure of a DSDM Timebox as presented in the Handbook?
AKick-off, Refinement, Investigation, Close-Out, Consolidation.
BKick-off, Investigation, Refinement, Consolidation, Close-Out.
CInvestigation, Kick-off, Consolidation, Refinement, Close-Out.
DPlanning, Execution, Monitoring and Controlling, Closure.
Show answer & explanation
B is correct. The Handbook describes a Timebox as running through Kick-off (confirming objectives, scope, and priorities), Investigation, Refinement (iterative build and test), Consolidation (finishing off and ensuring completeness), and Close-Out (formal review with stakeholders).
↗ the AgileBA Handbook (Agile Business Consortium / APMG) — Prioritization and Timeboxing
Practise all 25 Prioritization and Timeboxing questions - start free → See the whole AgileBA Found. bank

Other AgileBA Found. areas

The same kind of free sample for every other section of the AgileBA Found. bank:

Agile Fundamentals and the Agile BA Role35 qRequirements, User Stories and Modelling35 qRoles, Responsibilities and Stakeholders30 qAgile Business Case, Estimating and Benefits25 q

Study Prioritization and Timeboxing with instant feedback

6 free questions · filter study mode by area and difficulty · error log with spaced repetition · no card, no dumps, no ads.

Create your free account →
Read next
ECBA vs CCBA vs CBAP: Which IIBA Certification Fits Your Experience Level? (2026) ECBA, CCBA or CBAP? The eligibility gate that picks for you, what the 2026 ECBA rewrite changed, and each credential's three-year cost, verified against IIBA. PMI-PBA vs CBAP: The Business Analysis Certification Decision, Settled with Data PMI-PBA ($405-555, 36 months of experience) vs CBAP ($495-650 all-in, 7,500 hours plus references): eligibility, exam mechanics, three-year cost, salary data.
ExamDeck is an independent study tool, not affiliated with, endorsed by, or sponsored by APMG. AgileBA Found. and related marks are trademarks of their respective owners, used for identification only. Exam facts checked against official APMG materials (as of August 2026); always confirm current details with the vendor before booking.