1/5 · Project Management Fundamentals and Core Concepts
A new project manager has just been assigned to lead an initiative. Before any planning work begins, the sponsor issues a signed document that formally authorizes the project's existence and grants the project manager the authority to apply organizational resources to project activities. What is this document?
AThe business case
BThe project charter
CThe stakeholder register
DThe project management plan
Show answer & explanation
B is correct. The project charter is the document that formally authorizes a project and gives the project manager authority to apply organizational resources to project activities. It is typically issued early, before detailed planning begins, and is one of the first fundamentals concepts tested on the CAPM exam.
↗ CAPM Examination Content Outline (2023 Exam Update) + PMBOK Guide and Agile Practice Guide fundamentals — Project Management Fundamentals and Core Concepts
2/5 · Project Management Fundamentals and Core Concepts · hard
A stakeholder asks the project manager to add a new feature that was not part of the originally approved scope. The project manager believes the change is small and could be completed quickly. According to basic change control practice, what should the project manager do next?
AImplement the change immediately since it appears small and will save time.
BRefuse to consider the request because the scope was already approved and can never change.
CApprove the change unilaterally without recording it, since the project manager has final say over scope.
DSubmit a formal change request and have its impact on scope, schedule, and cost assessed before any decision to implement it.
Show answer & explanation
D is correct. Basic change control practice requires that requested changes, regardless of perceived size, be submitted, assessed for impact, and formally approved or rejected before implementation, with the decision recorded in the change log. This protects the project baseline and ensures stakeholders understand the consequences of scope changes.
↗ CAPM Examination Content Outline (2023 Exam Update) + PMBOK Guide and Agile Practice Guide fundamentals — Project Management Fundamentals and Core Concepts
3/5 · Project Management Fundamentals and Core Concepts
A project manager is deciding how, when, and to whom project status updates will be distributed throughout the project, including the format and frequency appropriate for each stakeholder group. Which document should capture this information?
ACommunications management plan.
BStakeholder register.
CRisk register.
DIssue log.
Show answer & explanation
A is correct. The communications management plan specifies the communication needs of stakeholders, including what information will be shared, the format, frequency, and delivery method, and who is responsible for distributing it. It is built using inputs such as the stakeholder register but serves a distinct planning purpose.
↗ CAPM Examination Content Outline (2023 Exam Update) + PMBOK Guide and Agile Practice Guide fundamentals — Project Management Fundamentals and Core Concepts
4/5 · Project Management Fundamentals and Core Concepts
A manufacturing plant runs the same production line every day using the same repeated processes to make an established product. Separately, the company starts a one-time initiative to design and build a brand-new production line, which will conclude once the line is built and handed over to the plant's daily operations team. How should these two efforts be classified?
AThe daily production work is operations (ongoing, repetitive work producing the same output), while building the new line is a project (a temporary endeavor with a definite start and end).
BThe daily production work is a program, and building the new line is a portfolio.
CBoth are projects, because both require organizational resources and coordinated work to be completed.
DThe daily production work is a project because it produces a product, and building the new line is operations because it follows standard construction steps.
Show answer & explanation
A is correct. Operations are ongoing and repetitive, sustaining the business by producing the same product or service over time. A project is a temporary endeavor undertaken to create a unique product, service, or result, with a defined beginning and end. Programs and portfolios refer to groups of related projects/activities managed together for broader benefits or strategic alignment, which does not apply to either single effort described here.
↗ CAPM Examination Content Outline (2023 Exam Update) + PMBOK Guide and Agile Practice Guide fundamentals — Project Management Fundamentals and Core Concepts
5/5 · Project Management Fundamentals and Core Concepts
Midway through execution, a team lead reports that a key data feed has already stopped working, halting a scheduled task. Separately, the project manager notes that the same vendor's history suggests future feeds might be delayed. How should these two items be logged?
ABoth belong in the issue log, because the issue log captures anything that could ever affect the project schedule.
BThe data feed failure is a risk because it originated with a third party, while the future delay is an issue because it is expected to happen.
CBoth belong in the risk register, since risk registers are used to track anything related to a vendor.
DThe data feed failure is an issue (already occurred, tracked in the issue log), while the possible future delay is a risk (an uncertain future event, tracked in the risk register).
Show answer & explanation
D is correct. An issue is a current fact or condition that is already impacting or has already impacted the project and is tracked in the issue log, while a risk is an uncertain future event or condition that, if it occurs, has a positive or negative effect on the project and is tracked in the risk register. Confusing an already-occurred problem with an uncertain future one leads to the wrong tool being used to manage it.
↗ the CAPM Examination Content Outline (PMI, 2023) — Project Management Fundamentals and Core Concepts
Practise all 49 Project Management Fundamentals and Core Concepts questions - start free → See the whole CAPM® bank

Other CAPM® areas

The same kind of free sample for every other section of the CAPM® bank:

Predictive, Plan-Based Methodologies30 qAgile Frameworks/Methodologies32 qBusiness Analysis Frameworks39 q

Study Project Management Fundamentals and Core Concepts with instant feedback

6 free questions · filter study mode by area and difficulty · error log with spaced repetition · no card, no dumps, no ads.

Create your free account →
Read next
Is the PMP Still Worth It in 2026? The New Price, the Salary Data, and Four Cheaper Routes PMP costs $445 (members) or $675 since 6 August 2026. The three-year cost, what PMI's salary survey does and does not prove, and four cheaper routes.
ExamDeck is an independent study tool, not affiliated with, endorsed by, or sponsored by PMI. CAPM® and related marks are trademarks of their respective owners, used for identification only. Exam facts checked against official PMI materials (as of August 2026); always confirm current details with the vendor before booking.