PMI-RMP® · PMI · Risk Identification · Bank updated 2026-07-03
PMI-RMP® practice questions: Risk Identification
5 free questions from 33 on this area · answer and explanation for each · no sign-up
These 5 questions come from the Risk Identification section of our PMI-RMP® bank (33 questions on this area, which carries 23% of the real exam). Every question is original, with the correct answer explained and linked to the source it is drawn from.
1/5 · Risk Identification · easy
During a risk identification workshop, the facilitator distributes a document listing generic risk categories such as PESTLE (Political, Economic, Social, Technological, Legal, Environmental) to help the team think broadly about possible sources of risk. What is this document called?
ARisk breakdown structure (RBS)
BAssumptions log
CPrompt list
DRisk register
Show answer & explanation
2/5 · Risk Identification
The project has a fixed, non-negotiable go-live date mandated by a regulatory deadline and a budget cap set by the sponsor. The risk manager reviews these fixed limitations specifically to identify risks that could arise from the lack of flexibility they impose on the project. This activity is an example of what?
AAssumption analysis
BSensitivity analysis
CStakeholder analysis
DConstraint analysis
Show answer & explanation
3/5 · Risk Identification · hard
Two risks are logged in the risk register. Risk A has a probability of 60% and a moderate cost impact, with an estimated trigger window roughly 8 months from now. Risk B has a probability of 25% and the same moderate cost impact, but its trigger window falls within the next 10 days due to an imminent contract renewal deadline. When assigning review priority based on urgency, which risk should be flagged for more immediate attention, and why?
ARisk B, because its imminent trigger window gives the team little time to plan and implement a response despite its lower probability
BRisk A, because its higher probability outweighs any timing consideration
CNeither risk requires urgent flagging since both have only moderate impact
DBoth risks should receive identical review priority because their impact ratings are the same
Show answer & explanation
4/5 · Risk Identification
Organizational policy states: 'Any individual risk with a potential schedule impact greater than 15 working days must be escalated to the steering committee, regardless of its probability.' In risk management terminology, this policy describes a:
ARisk appetite statement in isolation
BRisk trigger
CRisk threshold
DContingency reserve policy
Show answer & explanation
5/5 · Risk Identification
A risk practitioner builds an identification checklist using the lessons-learned repository from five prior, similar infrastructure projects. The current project, however, introduces a first-of-its-kind cloud migration component that none of the prior projects included. What is the MOST significant limitation of relying primarily on this checklist for the current effort?
AChecklists are inherently biased toward negative risks and will cause every opportunity to be overlooked entirely.
BChecklists require statistical validation through simulation modeling before they can be applied to any new project.
CA checklist reflects only risks previously encountered, so while thorough for known categories, it is likely blind to risks unique to the novel cloud migration component and should be supplemented with other techniques.
DChecklists should never be built from historical data, since reusing prior project information violates good identification practice.
Show answer & explanation
C is correct. Checklist analysis is efficient and thorough for risk categories that have occurred before, but its scope is bounded by the historical data used to build it. Because the current project contains an unprecedented element, the facilitator needs to supplement the checklist with techniques such as assumption analysis or expert interviews to surface risks the checklist cannot anticipate.
↗ the PMI-RMP Examination Content Outline — Risk Identification
Other PMI-RMP® areas
The same kind of free sample for every other section of the PMI-RMP® bank:
Study Risk Identification with instant feedback
6 free questions · filter study mode by area and difficulty · error log with spaced repetition · no card, no dumps, no ads.
Create your free account →
ExamDeck is an independent study tool, not affiliated with, endorsed by, or sponsored by PMI. PMI-RMP® and related marks are trademarks of their respective owners, used for identification only. Exam facts checked against official PMI materials (as of August 2026); always confirm current details with the vendor before booking.