1/5 · Risk Strategy and Planning
A risk manager is preparing to identify risks for a multi-country infrastructure project. Leadership wants a structured view of how upcoming elections, new trade tariffs, and tightening environmental regulations across the involved countries could affect the project. Which technique is BEST suited to capture these external risk drivers?
ARACI matrix
BProbability and impact matrix
CPESTLE analysis
DSWOT analysis
Show answer & explanation
C is correct. PESTLE analysis is the recommended technique for assessing macro-environmental factors — political, economic, social, technological, legal, and environmental — that can create threats or opportunities, making it the appropriate tool for this cross-border scenario.
↗ the PMI-RMP Examination Content Outline (January 2023) + PMI's Standard for Risk Management in Portfolios, Programs, and Projects + PMBOK Guide risk content — Risk Strategy and Planning
2/5 · Risk Strategy and Planning · easy
Which term describes a specific, measurable boundary of acceptable variation in a risk metric — for example, 'no more than 10% schedule slippage' — that triggers a defined response when exceeded?
ARisk attitude
BRisk appetite
CRisk threshold
DRisk category
Show answer & explanation
C is correct. Risk appetite is the broad, general level of risk an organization is willing to accept, while risk thresholds translate that appetite into specific, measurable limits on particular objectives that trigger action when crossed.
↗ the PMI-RMP Examination Content Outline (January 2023) + PMI's Standard for Risk Management in Portfolios, Programs, and Projects + PMBOK Guide risk content — Risk Strategy and Planning
3/5 · Risk Strategy and Planning · easy
A risk manager has just been assigned to a project that is already underway. Before facilitating any risk identification workshops, which activity should the risk manager perform FIRST?
ADistribute a risk questionnaire to all stakeholders to crowdsource a list of risks
BBuild the risk breakdown structure (RBS) so risks can be categorized as they are identified
CReview the business case, project charter, and other foundational documents to understand objectives, assumptions, and constraints
DInterview the project sponsor about the worst-case financial exposure of the project
Show answer & explanation
C is correct. PMI doctrine holds that risk planning begins with preliminary document analysis (charter, business case, scope statement, etc.) so the risk manager understands objectives, assumptions, and constraints before engaging stakeholders or building planning artifacts. Skipping this step risks misaligning the risk process with actual project intent.
↗ the PMI-RMP Examination Content Outline (January 2023) + PMI's Standard for Risk Management in Portfolios, Programs, and Projects + PMBOK Guide risk content — Risk Strategy and Planning
4/5 · Risk Strategy and Planning · hard
The risk management plan's RACI matrix designates the project manager as 'Accountable' and functional team leads as 'Responsible' for executing risk responses within their respective areas. A functional lead objects, insisting that only the risk manager should be accountable for all risk outcomes on the project. What should the risk manager do?
ARevise the RACI matrix so the risk manager is Accountable for all risk responses, since risk ownership should be centralized in the risk manager
BExplain that accountability for a given risk response typically rests with the person best positioned to control the underlying work, while the risk manager facilitates the overall risk process, and confirm this in the risk management plan
CIgnore the objection, since a RACI matrix, once published, cannot be revisited
DEscalate the disagreement immediately to the sponsor for a ruling, without first attempting to clarify roles directly with the functional lead
Show answer & explanation
B is correct. In risk management planning, the risk manager typically facilitates and coordinates the overall process, while accountability for executing a specific risk response is assigned to the person who controls the relevant work (the risk owner). When roles are misunderstood, the risk manager should clarify directly with the stakeholder and confirm the rationale in the risk management plan before considering escalation.
↗ the PMI-RMP Examination Content Outline (January 2023) + PMI's Standard for Risk Management in Portfolios, Programs, and Projects + PMBOK Guide risk content — Risk Strategy and Planning
5/5 · Risk Strategy and Planning · hard
Two projects in the same organization are being planned. Project X is a three-month internal process update with a single stakeholder group. Project Y is an 18-month multi-vendor system integration under regulatory oversight. The organization has one standard risk management template. What is the most defensible approach to developing the risk management plan for each?
AUse the template for Project Y only and skip formal risk planning for Project X, since a short internal project carries no meaningful risk.
BApply the organizational template exactly as written to both projects, since consistency across projects matters more than fit to each project's context.
CTailor the depth, frequency, and resourcing of risk activities to each project's complexity — a lighter approach for Project X and a more rigorous approach, including dedicated risk resources and reporting cadence, for Project Y.
DRequire Project X to adopt the same risk budget and reporting cadence as Project Y so both projects can be benchmarked identically at the portfolio level.
Show answer & explanation
C is correct. Determining risk management deliverables requires assessing each project's complexity and scaling the budget, schedule, and resources devoted to risk activities accordingly; an organizational template is a starting point to be tailored, not applied identically regardless of context.
↗ the PMI-RMP Examination Content Outline — Risk Strategy and Planning
Practise all 32 Risk Strategy and Planning questions - start free → See the whole PMI-RMP® bank

Other PMI-RMP® areas

The same kind of free sample for every other section of the PMI-RMP® bank:

Risk Identification33 qRisk Analysis33 qRisk Response23 qMonitor and Close Risks29 q

Study Risk Strategy and Planning with instant feedback

6 free questions · filter study mode by area and difficulty · error log with spaced repetition · no card, no dumps, no ads.

Create your free account →
Read next
PRINCE2 Foundation vs Practitioner: What Changes, What It Costs, Who Needs Which PRINCE2 Foundation (60 questions, closed book) vs Practitioner (scenarios, open book), both at 60% to pass. What each bundle costs and who needs which. Is the PMP Still Worth It in 2026? The New Price, the Salary Data, and Four Cheaper Routes PMP costs $445 (members) or $675 since 6 August 2026. The three-year cost, what PMI's salary survey does and does not prove, and four cheaper routes.
ExamDeck is an independent study tool, not affiliated with, endorsed by, or sponsored by PMI. PMI-RMP® and related marks are trademarks of their respective owners, used for identification only. Exam facts checked against official PMI materials (as of August 2026); always confirm current details with the vendor before booking.