1/5 · Leadership for PI Planning · easy
During the team breakout sessions of PI Planning, who is primarily responsible for facilitating the team's own planning process, such as timeboxing discussions and helping resolve planning impediments?
ASystem Architect
BRelease Train Engineer
CScrum Master/Team Coach
DBusiness Owner
Show answer & explanation
C is correct. The Scrum Master/Team Coach facilitates the team's breakout session, guiding the team through capacity/load planning, drafting PI objectives, and surfacing risks and dependencies, while the RTE facilitates the PI Planning event as a whole across all teams.
↗ the SAFe 6.0 framework (framework.scaledagile.com) + the official SAFe Product Owner/Product Manager course content — Leadership for PI Planning
2/5 · Leadership for PI Planning
During the Day 2 ROAM session, a team surfaces a risk that depends on a decision another team won't make until later in the Program Increment. The ART cannot resolve it on the spot, so a named individual agrees to track it and report status at future ART syncs. How should this risk be categorized?
AResolved
BAccepted
COwned
DMitigated
Show answer & explanation
C is correct. A risk is categorized as Owned when it cannot be resolved during the ROAM session but a specific person takes responsibility for monitoring it and reporting progress; this differs from Accepted (no action needed), Mitigated (an active plan exists to reduce impact), and Resolved (already settled).
↗ the SAFe 6.0 framework (framework.scaledagile.com) + the official SAFe Product Owner/Product Manager course content — Leadership for PI Planning
3/5 · Leadership for PI Planning
During a Day 1 team breakout session, the team needs to clarify acceptance criteria and break a Feature down into candidate stories for the Team Backlog. Which role primarily leads this content-level work with the team?
ABusiness Owner
BProduct Manager
CProduct Owner
DRelease Train Engineer
Show answer & explanation
C is correct. Consistent with the SAFe PO/PM responsibility split, the Product Owner works directly with the team during breakout sessions to elaborate Features into stories, clarify acceptance criteria, and help draft the Team Backlog, while the Product Manager remains focused on program-level Features and the roadmap.
↗ the SAFe 6.0 framework (framework.scaledagile.com) + the official SAFe Product Owner/Product Manager course content — Leadership for PI Planning
4/5 · Leadership for PI Planning · easy
On the Titan Agile Release Train, several new Scrum Masters are unsure which role owns timeboxing the agenda, arranging logistics, and keeping the PI Planning event moving across both days. Which role holds this responsibility?
AThe Product Manager, since the event exists to plan delivery of the program backlog
BThe Release Train Engineer, who serves as chief planner and facilitator of ART events including PI Planning
CThe Solution Train Engineer, because only Solution-level roles may facilitate any ART-level event
DThe Product Owner, since teams are the ones executing the resulting plan
Show answer & explanation
B is correct. SAFe assigns facilitation of the PI Planning event—agenda, logistics, and keeping the two days on track—to the Release Train Engineer as a servant leader for the train. Product Management and Product Owners contribute essential content and decisions during the event but do not run it. This distinction is a common point of confusion for POPM candidates who conflate 'owning content' with 'facilitating the event.'
↗ the SAFe 6.0 framework (framework.scaledagile.com) — POPM — Leadership for PI Planning
5/5 · Leadership for PI Planning
During a team breakout session, the Product Owner for Team Phoenix is expected to actively contribute to several planning activities. Which of the following best reflects that expected involvement?
AIndependently assigning business value scores to the team's own PI objectives before the Business Owners arrive
BWorking with the team to identify and prioritize stories, and helping formulate the team's draft PI objectives
CBuilding the program board for every team on the train to ensure a single consistent format
DDeciding the team's iteration-by-iteration velocity alone, without input from the rest of the team during breakout
Show answer & explanation
B is correct. During breakout sessions, the Product Owner works closely with the team to define and prioritize stories, negotiate content, and help shape the team's draft PI objectives, which are later refined with Business Owner input. Business value scoring, team capacity decisions, and cross-team artifacts remain shared or other-role responsibilities. Overstating the Product Owner's solo authority in these areas is a common exam distractor pattern.
↗ the SAFe 6.0 framework (framework.scaledagile.com) — POPM — Leadership for PI Planning
Practise all 25 Leadership for PI Planning questions - start free → See the whole SAFe POPM bank

Other SAFe POPM areas

The same kind of free sample for every other section of the SAFe POPM bank:

Product Owner/Product Management Roles and Responsibilities24 qPI Planning Preparation33 qIteration Execution42 qPI Execution24 q

Study Leadership for PI Planning with instant feedback

6 free questions · filter study mode by area and difficulty · error log with spaced repetition · no card, no dumps, no ads.

Create your free account →
Read next
PSM I vs CSM in 2026: Price, Difficulty, and Which One Employers Actually Ask For PSM I vs CSM: a $200 self-study exam vs a mandatory course, 85% pass mark vs open-book 74%, lifetime validity vs renewal every two years. Verified August 2026.
ExamDeck is an independent study tool, not affiliated with, endorsed by, or sponsored by Scaled Agile. SAFe POPM and related marks are trademarks of their respective owners, used for identification only. Exam facts checked against official Scaled Agile materials (as of August 2026); always confirm current details with the vendor before booking.