1/5 · PI Execution · easy
Which three parts, held in sequence at the end of a Program Increment, make up the SAFe 6.0 Inspect and Adapt (I&A) workshop?
ATeam Retrospective, Backlog Refinement, and Iteration Planning.
BPI Planning, ART Sync, and Scrum of Scrums.
CPI System Demo, Quantitative and Qualitative Measurement, and the Retrospective and Problem-Solving workshop.
DSprint Review, Sprint Retrospective, and Sprint Planning.
Show answer & explanation
C is correct. SAFe 6.0's I&A workshop consists of the PI System Demo (an integrated view of the full PI's work), Quantitative and Qualitative Measurement (reviewing metrics like the Program Predictability Measure), and the Retrospective and Problem-Solving workshop (root-causing the PI's biggest issue).
↗ the SAFe 6.0 framework (framework.scaledagile.com) + the official SAFe Product Owner/Product Manager course content — PI Execution
2/5 · PI Execution
During Iteration 3 of a PI, a team learns that a dependency from another team will arrive a full Iteration later than planned, blocking one of its committed stories. What should the team's Product Owner do first, per SAFe 6.0 guidance?
AReorder the Team Backlog to pull forward ready, unblocked stories of similar value so the team can keep delivering toward the Iteration Goal while the dependency resolves.
BImmediately cancel the PI Objective associated with the blocked story, since it can no longer be met.
CInstruct the team to keep working on the blocked story until the dependency arrives, to protect the original Iteration Plan.
DAsk the Release Train Engineer to add extra Iterations to the PI so the blocked story can still be completed on schedule.
Show answer & explanation
A is correct. When a dependency is delayed, the Product Owner should reprioritize the Team Backlog toward unblocked, valuable work so the team continues progressing toward its Iteration Goal, rather than idling or prematurely abandoning the affected PI Objective.
↗ the SAFe 6.0 framework (framework.scaledagile.com) + the official SAFe Product Owner/Product Manager course content — PI Execution
3/5 · PI Execution
During PI Execution, who is primarily responsible for tracking progress on Features in the Program Backlog and coordinating with Product Owners across the ART, while Product Owners focus on managing and prioritizing their own Team Backlogs?
AThe System Architect/Engineering function.
BThe Scrum Master.
CThe Business Owner.
DThe Product Manager.
Show answer & explanation
D is correct. SAFe 6.0 maintains a clear PO/PM split: the Product Manager works at the program level with Features, the Program Backlog, and the roadmap, coordinating with the ART's Product Owners, while each Product Owner manages stories and priorities within their own Team Backlog.
↗ the SAFe 6.0 framework (framework.scaledagile.com) + the official SAFe Product Owner/Product Manager course content — PI Execution
4/5 · PI Execution
Midway through Iteration 4 of the current PI, a Product Owner learns that a Feature owned by a different ART, on which one of the team's committed stories depends, will now be delivered two iterations late. The dependency was originally mapped on the Program Board during PI Planning. What is the MOST appropriate immediate action per SAFe 6.0?
AAsk the Business Owners to halt the PI immediately and convene an unplanned PI Planning event to re-sequence the dependency across ARTs.
BUnilaterally remove the affected story from the current Iteration without discussing it with the team, since the Product Owner alone owns and controls the Team Backlog.
CRaise the dependency at the next ART Sync (Scrum of Scrums / PO Sync) so the RTE can help coordinate with the other ART, update the Program Board, log the risk using ROAM, and adjust the Team Backlog with the team as needed.
DTake no action until the System Demo, since cross-ART dependencies are only reviewed and adjusted at that event.
Show answer & explanation
C is correct. In SAFe 6.0, cross-ART dependencies identified during PI Planning are visualized on the Program Board and actively managed throughout PI Execution via the RTE-facilitated ART Sync (Scrum of Scrums and PO Sync). When a dependency risk materializes, it should be surfaced there, tracked using ROAM, and only then reflected in the Team Backlog through collaborative re-sequencing with the team — not through unilateral PO action, an emergency re-plan, or silence until the System Demo.
↗ the SAFe 6.0 framework (framework.scaledagile.com) + the official SAFe Product Owner/Product Manager course content — PI Execution
5/5 · PI Execution
During the problem-solving workshop portion of Inspect and Adapt, the ART names 'inconsistent test environment availability' as its top impediment. Which practice is most appropriate for uncovering the systemic causes before improvement items are proposed?
AA fishbone (Ishikawa) diagram or a '5 Whys' analysis to trace contributing causes across the ART.
BSeparate retrospectives held independently by each team with no cross-team discussion.
CA WSJF calculation to decide which team should own the environment first.
DA vote among Business Owners to decide which team is at fault.
Show answer & explanation
A is correct. The Inspect and Adapt problem-solving workshop typically applies structured root-cause techniques such as fishbone diagrams or 5 Whys, examined at the whole-ART level, so the resulting improvement items address the true systemic cause rather than a symptom.
↗ the SAFe 6.0 framework (framework.scaledagile.com) — POPM — PI Execution
Practise all 24 PI Execution questions - start free → See the whole SAFe POPM bank

Other SAFe POPM areas

The same kind of free sample for every other section of the SAFe POPM bank:

Product Owner/Product Management Roles and Responsibilities24 qPI Planning Preparation33 qLeadership for PI Planning25 qIteration Execution42 q

Study PI Execution with instant feedback

6 free questions · filter study mode by area and difficulty · error log with spaced repetition · no card, no dumps, no ads.

Create your free account →
Read next
PSM I vs CSM in 2026: Price, Difficulty, and Which One Employers Actually Ask For PSM I vs CSM: a $200 self-study exam vs a mandatory course, 85% pass mark vs open-book 74%, lifetime validity vs renewal every two years. Verified August 2026.
ExamDeck is an independent study tool, not affiliated with, endorsed by, or sponsored by Scaled Agile. SAFe POPM and related marks are trademarks of their respective owners, used for identification only. Exam facts checked against official Scaled Agile materials (as of August 2026); always confirm current details with the vendor before booking.