SAFe SSM · Scaled Agile · Supporting ART Events · Bank updated 2026-09-12

SAFe SSM practice questions: Supporting ART Events

5 free questions from 30 on this area · answer and explanation for each · no sign-up

These 5 questions come from the Supporting ART Events section of our SAFe SSM bank (30 questions on this area, which carries 28% of the real exam). Every question is original, with the correct answer explained and linked to the source it is drawn from.

Start 6 free in study mode → All SAFe SSM sample questions
1/5 · Supporting ART Events · easy
Which statement best describes the purpose and typical participants of the PO Sync?
AA once-per-PI event where Business Owners individually score every team's velocity.
BThe event where Scrum Masters/Team Coaches discuss cross-team impediments; also known as the Coach Sync.
CA meeting where Scrum Masters resolve team-level technical debt and refactor the codebase together.
DA brief, cadence-based meeting, typically facilitated by the RTE or Product Manager, where Product Owners align on progress toward PI Objectives, dependencies, and scope adjustments.
Show answer & explanation
D is correct. The PO Sync is one of the two ART sync events. It is typically a short, frequent meeting where Product Owners (often with the Product Manager and/or RTE) keep each other informed of progress, discuss cross-team dependencies, and decide whether the plan needs adjusting mid-PI.
↗ the SAFe 6.0 framework (framework.scaledagile.com) + the official SAFe Scrum Master course content - Supporting ART Events
2/5 · Supporting ART Events
Which combination BEST describes the intended purposes of the Innovation and Planning (IP) Iteration in a Program Increment?
AIt is a Hardening and Stabilization phase reserved for QA to fix defects before release, similar to a traditional waterfall test phase.
BIt provides dedicated time for innovation, exploration, hackathons, PI Planning preparation, and the Inspect and Adapt event, while also serving as an estimating guardband.
CIt is an additional Iteration used exclusively to finish leftover Iteration-level stories from the previous PI.
DIt exists solely so teams can take a mandatory week of vacation between Program Increments.
Show answer & explanation
B is correct. The IP Iteration is a dedicated Iteration at the end of each PI that supports innovation, gives teams time for exploration and PI Planning readiness, and hosts the Inspect and Adapt event. It also functions as an estimating guardband, absorbing variability, and should not be treated as extra capacity to finish undone work.
↗ the SAFe 6.0 framework (framework.scaledagile.com) + the official SAFe Scrum Master course content - Supporting ART Events
3/5 · Supporting ART Events · hard
Midway through a PI, a Scrum Master/Team Coach discovers that a cross-team dependency impediment cannot be resolved within their own team and requires a decision affecting two other teams' priorities. What is the MOST appropriate course of action, consistent with SAFe's approach to coaching the ART?
ARaise the impediment through the ART sync (e.g., Coach Sync) and, if needed, engage the RTE, who facilitates cross-team dependency resolution at the ART level.
BIgnore the impediment since it does not solely belong to the Scrum Master/Team Coach's own team, and let each affected team discover and resolve it independently.
CThe Scrum Master/Team Coach directly instructs the other two teams' Product Owners to reprioritize their backlogs to unblock their own team.
DWait until the next PI Planning event to raise the impediment, since mid-PI escalation is discouraged in SAFe.
Show answer & explanation
A is correct. Coaching the ART means recognizing when an impediment exceeds a single team's ability to resolve it and using the appropriate escalation path: raising it at the ART sync and engaging the RTE, who is responsible for facilitating cross-team dependency and impediment resolution throughout the PI, not just at PI Planning.
↗ the SAFe 6.0 framework (framework.scaledagile.com) + the official SAFe Scrum Master course content - Supporting ART Events
4/5 · Supporting ART Events
During Team Breakout #1 on Day 1 of PI Planning, a team is drafting its plan and discovers it depends on a component team it does not usually work with. As the team's Scrum Master/Team Coach, what is the MOST appropriate action?
AFacilitate the team to finish drafting PI objectives and stories, then visibly flag the dependency and any related risk on the program board for cross-team visibility.
BPersonally decide how to resolve the dependency and notify the other team's manager afterward.
CTell the team to disregard the dependency since it will surface naturally at the System Demo.
DAssign the dependent work directly to specific team members without team discussion, to save time.
Show answer & explanation
A is correct. During team breakouts, the Scrum Master/Team Coach facilitates the team's own planning while ensuring cross-team dependencies and risks are captured visibly (e.g., on the program board) so the ART can address them collaboratively rather than in isolation.
↗ the SAFe 6.0 framework (framework.scaledagile.com) + the official SAFe Scrum Master course content — Supporting ART Events
5/5 · Supporting ART Events · hard
During the Inspect and Adapt workshop, the ART first conducts the PI System Demo, then moves into a distinct activity where the actual business value achieved is compared against the planned business value for each team's PI objectives. What is this second activity called?
ATeam Breakout #2.
BConfidence vote.
CQuantitative measurement.
DBacklog refinement.
Show answer & explanation
C is correct. The Inspect and Adapt workshop has three parts: the PI System Demo, quantitative measurement (comparing planned versus actual business value and other metrics), and the retrospective and problem-solving workshop.
↗ the SAFe 6.0 framework (framework.scaledagile.com) + the official SAFe Scrum Master course content — Supporting ART Events
Practise all 30 Supporting ART Events questions - start free → See the whole SAFe SSM bank

Other SAFe SSM areas

The same kind of free sample for every other section of the SAFe SSM bank:

Introducing Scrum in SAFe28 qDefining the Scrum Master/Team Coach Role30 qSupporting Team Events21 q

Study Supporting ART Events with instant feedback

6 free questions · filter study mode by area and difficulty · error log with spaced repetition · no card, no dumps, no ads.

Create your free account →
Read next
PSM I vs CSM in 2026: Price, Difficulty, and Which One Employers Actually Ask For PSM I vs CSM: a $200 self-study exam vs a mandatory course, 85% pass mark vs open-book 74%, lifetime validity vs renewal every two years. Verified August 2026.
ExamDeck is an independent study tool, not affiliated with, endorsed by, or sponsored by Scaled Agile. SAFe SSM and related marks are trademarks of their respective owners, used for identification only. Exam facts checked against official Scaled Agile materials (as of August 2026); always confirm current details with the vendor before booking.