Home › SAFe SSM › Practice questions › Supporting ART Events
SAFe SSM · Scaled Agile · Supporting ART Events · Bank updated 2026-09-28

SAFe SSM practice questions: Supporting ART Events

5 free questions from 30 on this area · answer and explanation for each · no sign-up

These 5 questions come from the Supporting ART Events section of our SAFe SSM bank (30 questions on this area, which carries 28% of the real exam). Every question is original, with the correct answer explained and linked to the source it is drawn from.

Try 6 free SAFe SSM questions → All SAFe SSM sample questions

Free: 6 questions in study mode, no card. All 30 Supporting ART Events questions and the full SAFe SSM bank: $15 one-time.

1/5 · Supporting ART Events · easy
Which statement best describes the purpose and typical participants of the PO Sync?
AA once-per-PI meeting where Business Owners individually score every team's velocity and use those scores to re-rank the business value of the teams' committed PI Objectives.
BA regular meeting where Scrum Masters/Team Coaches discuss cross-team impediments and dependencies with the RTE to keep the ART's teams aligned and on schedule.
CA recurring meeting where Scrum Masters and System Architects resolve team-level technical debt and agree on refactoring priorities across the ART's shared codebase.
DA short, regular meeting, typically led by Product Management and System Architects, where Product Owners align on PI Objective progress, dependencies, and scope adjustments.
Answer: D. The PO Sync is one of the two ART sync conversations. It is typically a short, frequent meeting, led by Product Management and System Architects, where Product Owners (with the RTE and Business Owners taking part) keep each other informed of progress, discuss cross-team dependencies, and decide whether the plan needs adjusting mid-PI. Source: the SAFe 6.0 framework (framework.scaledagile.com) + the official SAFe Scrum Master course content - Supporting ART Events
2/5 · Supporting ART Events
Which combination BEST describes the intended purposes of the Innovation and Planning (IP) Iteration in a Program Increment?
AIt is a Hardening and Stabilization Iteration reserved for QA to fix the PI's defects before release, with innovation deferred until after the next PI Planning.
BIt provides time for innovation, exploration, hackathons, PI Planning preparation, and the Inspect and Adapt event, and also serves as an estimating buffer.
CIt is a planned break between Program Increments, when teams take time off and innovation and exploration wait for the next PI's Iterations.
DIt provides time for innovation, hackathons and PI Planning prep, while Inspect and Adapt moves to the next PI's first Iteration.
Answer: B. The IP Iteration is a dedicated Iteration at the end of each PI that supports innovation, gives teams time for exploration and PI Planning readiness, and hosts the Inspect and Adapt event. It also functions as an estimating guardband, absorbing variability, and should not be treated as extra capacity to finish undone work. Source: the SAFe 6.0 framework (framework.scaledagile.com) + the official SAFe Scrum Master course content - Supporting ART Events
3/5 · Supporting ART Events · hard
Midway through a PI, a Scrum Master/Team Coach discovers that a cross-team dependency impediment cannot be resolved within their own team and requires a decision affecting two other teams' priorities. What is the MOST appropriate course of action, consistent with SAFe's approach to coaching the ART?
ARaise the impediment through the ART sync (e.g., Coach Sync) and, if needed, engage the RTE, who facilitates cross-team dependency resolution at the ART level.
BIgnore the impediment since it does not solely belong to the Scrum Master/Team Coach's own team, and let each affected team discover and resolve it independently.
CThe Scrum Master/Team Coach directly instructs the other two teams' Product Owners to reprioritize their backlogs to unblock their own team.
DWait until the next PI Planning event to raise the impediment, since mid-PI escalation is discouraged in SAFe.
Answer: A. Coaching the ART means recognizing when an impediment exceeds a single team's ability to resolve it and using the appropriate escalation path: raising it at the ART sync and engaging the RTE, who is responsible for facilitating cross-team dependency and impediment resolution throughout the PI, not just at PI Planning. Source: the SAFe 6.0 framework (framework.scaledagile.com) + the official SAFe Scrum Master course content - Supporting ART Events
4/5 · Supporting ART Events
During Team Breakout #1 on Day 1 of PI Planning, a team is drafting its plan and discovers it depends on a component team it does not usually work with. As the team's Scrum Master/Team Coach, what is the MOST appropriate action?
AFacilitate the team's drafting of PI objectives and stories, and make the dependency and any related risk visible on the ART planning board for the other teams.
BPersonally decide how the dependency will be resolved, agree it with the component team's manager, and inform the team afterward so its planning time in the breakout is not lost.
CTell the team to keep drafting and set the dependency aside for now, since it will surface naturally during integration and can be handled at the first System Demo of the PI.
DAsk the RTE to assign the dependent work to the component team centrally, so the dependency is settled before the draft plan review.
Answer: A. During team breakouts, the Scrum Master/Team Coach facilitates the team's own planning while ensuring cross-team dependencies and risks are captured visibly (e.g., on the ART planning board) so the ART can address them collaboratively rather than in isolation. Source: the SAFe 6.0 framework (framework.scaledagile.com) + the official SAFe Scrum Master course content — Supporting ART Events
5/5 · Supporting ART Events · hard
During the Inspect and Adapt workshop, the ART first conducts the PI System Demo, then moves into a distinct activity where the actual business value achieved is compared against the planned business value for each team's PI objectives. What is this second activity called?
ATeam Breakout #2 and the draft plan review.
BConfidence vote and plan rework.
CQuantitative and Qualitative Measurement.
DBacklog refinement and Iteration Review.
Answer: C. The Inspect and Adapt workshop has three parts: the PI System Demo, Quantitative and Qualitative Measurement (comparing planned versus actual business value and other metrics), and the Retrospective and Problem-Solving Workshop. Source: the SAFe 6.0 framework (framework.scaledagile.com) + the official SAFe Scrum Master course content — Supporting ART Events
Try 6 more free SAFe SSM questions → See the whole SAFe SSM bank

Other SAFe SSM areas

The same kind of free sample for every other section of the SAFe SSM bank:

Introducing Scrum in SAFe28 qDefining the Scrum Master/Team Coach Role30 qSupporting Team Events21 q

Practise SAFe SSM with instant feedback

6 free questions in study mode · no card · full SAFe SSM bank with area filters and the error log: $15 one-time · no dumps, no ads.

Start SAFe SSM free →
Read next
SAFe Scrum Master (SSM) vs PSM I: Which Scrum Master Certification for Which Organisation PSM I costs $200 once and never expires. SSM now has a $495 exam-only route and renews at $195 a year. Fees and formats verified at source, 24 Sep 2026. SAFe Certifications Explained: SA vs POPM vs SSM vs RTE (and Who Should Skip SAFe) SA, POPM, SSM and RTE: real exam formats, the pass marks Scaled Agile's own pages disagree on, retake fees and the $195/$295 annual renewal. Checked 18 Sep.
ExamDeck is an independent study tool, not affiliated with, endorsed by, or sponsored by Scaled Agile. SAFe SSM and related marks are trademarks of their respective owners, used for identification only. Exam facts checked against official Scaled Agile materials (as of November 2026); always confirm current details with the vendor before booking.