PRINCE2 7 Found. practice questions: Organizing practice

5 free questions from 14 on this area · answer and explanation for each · no sign-up

These 5 questions come from the Organizing practice section of our PRINCE2 7 Found. bank (14 questions on this area, which carries 9% of the real exam). Every question is original, with the correct answer explained and linked to the source it is drawn from.

Start 6 free in study mode → All PRINCE2 7 Found. sample questions
1/5 · Organizing practice · easy
PRINCE2 7 describes the project management team as operating across four levels of management. Reading from the top of the hierarchy downwards, which sequence is correct?
ADirecting, commissioning, managing, delivering
BCommissioning, directing, managing, delivering
CSponsoring, directing, managing, supporting
DCommissioning, directing, delivering, managing
Show answer & explanation
B is correct. PRINCE2 7's four levels run: commissioning (the corporate, programme or customer level that provides the mandate), directing (the project board), managing (the project manager) and delivering (team managers and team members). Each level delegates authority to, and expects reporting from, the level below.
↗ the official PRINCE2 7 Foundation syllabus + PRINCE2 7th edition manual 'Managing Successful Projects' (PeopleCert, 2023) — Organizing practice
2/5 · Organizing practice
Which of the following best describes the accountability of the executive role on a PRINCE2 7 project?
AThe executive is accountable for ensuring that supplier resources needed to produce the products are made available
BThe executive is ultimately accountable for the project throughout its life, supported by the senior user and senior supplier, and owns the business case
CThe executive is accountable for the day-to-day management of the project within limits set by the project board
DThe executive is accountable for specifying the project's benefits and confirming that user needs have been met
Show answer & explanation
B is correct. The executive owns the business case and is the single point of ultimate accountability for the project's success. The senior user and senior supplier support this accountability from user and supplier perspectives respectively, while day-to-day management is delegated to the project manager.
↗ the official PRINCE2 7 Foundation syllabus + PRINCE2 7th edition manual 'Managing Successful Projects' (PeopleCert, 2023) — Organizing practice
3/5 · Organizing practice
A project manager identifies that the current management stage is forecast to exceed its agreed tolerances. According to PRINCE2 7, what should the project manager do?
AEscalate the situation to the project board, typically via an exception report, since the deviation is beyond the project manager's delegated authority
BApprove the additional time and cost personally, since the project manager manages the project on a day-to-day basis
CInstruct the team manager to absorb the deviation within the team plan without informing the project board
DAsk project support to authorize the deviation on the project board's behalf
Show answer & explanation
A is correct. The project manager manages within the tolerances delegated by the project board. A forecast breach of tolerance falls outside that delegated authority and must be escalated to the project board, typically through an exception report, so the board can decide how to proceed.
↗ the official PRINCE2 7 Foundation syllabus + PRINCE2 7th edition manual 'Managing Successful Projects' (PeopleCert, 2023) — Organizing practice
4/5 · Organizing practice · hard
A project board delegates two distinct responsibilities to free up its own time: (1) authority to approve minor requests for change within an agreed budget and set of parameters, and (2) day-to-day administrative tasks such as maintaining the issue register and configuration records. Which PRINCE2 7 roles correspond to responsibilities (1) and (2) respectively?
AExecutive, then project manager
BProject assurance, then team manager
CChange authority, then project support
DSenior supplier, then senior user
Show answer & explanation
C is correct. The project board may delegate approval of changes within defined limits to a change authority, reducing the number of change requests the board itself must review. Project support provides administrative services, such as maintaining registers and configuration records, freeing the project manager and board to focus on decision-making.
↗ the official PRINCE2 7 Foundation syllabus + PRINCE2 7th edition manual 'Managing Successful Projects' (PeopleCert, 2023) — Organizing practice
5/5 · Organizing practice
Two departments each provide critical specialist resources to a project. The commissioning organization wants a representative from each department to jointly hold accountability for supplier interests on the Project Board, rather than appointing a single supplier representative. Which statement about PRINCE2 7 roles applies to this arrangement?
AIt is not permitted, because PRINCE2 7 requires every Project Board role, including Senior Supplier, to be held by exactly one individual at all times.
BIt is permitted, because a role such as Senior Supplier can be shared between more than one person, whereas the Executive role must always remain a single individual.
CIt is permitted only if a Change Authority is appointed specifically to arbitrate between the two Senior Suppliers on every supplier-related decision.
DIt is not permitted unless both representatives are also formally appointed as joint Executives, so that ultimate accountability is spread equally between the two departments.
Show answer & explanation
B is correct. PRINCE2 7 distinguishes between roles and the individuals who hold them: a single role can be shared by several people (for example, multiple Senior Suppliers representing different supplying departments) and, conversely, one person can hold more than one role. The only fixed constraint is that the Executive role must always be a single, named individual to preserve clear, ultimate accountability for the project.
↗ the official PRINCE2 7 Foundation syllabus (PeopleCert, 2023) — Organizing practice
Practise all 14 Organizing practice questions - start free → See the whole PRINCE2 7 Found. bank

Other PRINCE2 7 Found. areas

The same kind of free sample for every other section of the PRINCE2 7 Found. bank:

Key concepts of projects and PRINCE27 qThe PRINCE2 principles13 qPeople in successful projects17 qBusiness Case practice14 qPlans practice12 qQuality practice13 qRisk practice13 qIssues practice13 qProgress practice11 qThe PRINCE2 processes14 q

Study Organizing practice with instant feedback

6 free questions · filter study mode by area and difficulty · error log with spaced repetition · no card, no dumps, no ads.

Create your free account →
Read next
PRINCE2 Foundation vs Practitioner: What Changes, What It Costs, Who Needs Which PRINCE2 Foundation (60 questions, closed book) vs Practitioner (scenarios, open book), both at 60% to pass. What each bundle costs and who needs which.
ExamDeck is an independent study tool, not affiliated with, endorsed by, or sponsored by PeopleCert. PRINCE2 7 Found. and related marks are trademarks of their respective owners, used for identification only. Exam facts checked against official PeopleCert materials (as of September 2026); always confirm current details with the vendor before booking.