PRINCE2 7 Found. practice questions: Plans practice

5 free questions from 12 on this area · answer and explanation for each · no sign-up

These 5 questions come from the Plans practice section of our PRINCE2 7 Found. bank (12 questions on this area, which carries 8% of the real exam). Every question is original, with the correct answer explained and linked to the source it is drawn from.

Start 6 free in study mode → All PRINCE2 7 Found. sample questions
1/5 · Plans practice
During a management stage, the project manager forecasts that the remaining work will exceed the stage tolerances agreed with the project board. Following PRINCE2 7 guidance on levels of plan, what should the project manager produce to cover the period to the end of the current stage (or project)?
AAn updated project plan covering only the benefits realisation period.
BA team plan detailing the remaining work packages for each team.
CA fresh stage plan for the next management stage, moved forward to start immediately.
DAn exception plan, to be approved by the next higher authority before it replaces the plan it supersedes.
Show answer & explanation
D is correct. When a stage or project plan is forecast to exceed its tolerances, PRINCE2 7 requires an exception plan to be produced at the same level, covering the remaining period, and this plan replaces the one it supersedes once approved by the next level of management.
↗ the official PRINCE2 7 Foundation syllabus + PRINCE2 7th edition manual 'Managing Successful Projects' (PeopleCert, 2023) — Plans practice
2/5 · Plans practice
Within the product-based planning technique, which management product is used to record a product's purpose, composition, derivation and quality criteria?
AConfiguration item record
BProduct breakdown structure
CProduct description
DProduct flow diagram
Show answer & explanation
C is correct. A product description is written for each significant product (or type of product) identified in the product breakdown structure and defines what the product is for, what it is made up of, and how its quality will be checked, which is essential input to planning and quality control.
↗ the official PRINCE2 7 Foundation syllabus + PRINCE2 7th edition manual 'Managing Successful Projects' (PeopleCert, 2023) — Plans practice
3/5 · Plans practice · hard
Which statement about the project plan is correct according to PRINCE2 7?
AIt is produced by the team manager to schedule the work of a specific team.
BIt is replaced by the stage plan for the final management stage of the project.
CIt is mandatory, is developed during initiation, and gives the project board an overview statement of how and when the project's objectives are to be achieved.
DIt is optional and is only produced if the project board specifically requests a high-level overview of the work.
Show answer & explanation
C is correct. The project plan is a mandatory, project-level document produced during initiation that gives the project board the overview needed to authorise the project and make ongoing go/no-go decisions; it is updated (not replaced) as the project progresses through management stages.
↗ the official PRINCE2 7 Foundation syllabus + PRINCE2 7th edition manual 'Managing Successful Projects' (PeopleCert, 2023) — Plans practice
4/5 · Plans practice · easy
Within the levels of plan described in the Plans practice, which plan is created specifically to regain control when a stage or project is forecast to exceed its agreed tolerances, and takes the place of the remaining portion of the plan it replaces?
AException plan
BStage plan
CProject plan
DTeam plan
Show answer & explanation
A is correct. PRINCE2 7 recognizes project, stage, team (optional), and exception as levels of plan. The exception plan is produced only when a forecast shows tolerance will be exceeded, and it replaces the remaining part of the plan it supersedes, requiring approval from the same authority as the original plan.
↗ the official PRINCE2 7 Foundation syllabus (PeopleCert, 2023) — Plans practice
5/5 · Plans practice
During a planning workshop, a stakeholder insists that the product flow diagram for a project should display the resource allocated to each product and the calendar date each product is due, similar to a schedule. Which response best reflects the guidance on this diagram?
AThe product flow diagram must include resource names for each product but never shows dates
BThe product flow diagram is optional once a product breakdown structure exists, so its content is discretionary
CThe product flow diagram shows only the sequence in which products are to be delivered and the dependencies between them, not resources or dates
DThe product flow diagram replaces the schedule once the products have been sequenced
Show answer & explanation
C is correct. The product flow diagram is deliberately narrow in scope: it identifies products and the sequence/dependencies for delivering them. Resource allocation and dates belong to the scheduling step of the wider planning approach, so treating the flow diagram as a schedule is a common misreading.
↗ the official PRINCE2 7 Foundation syllabus (PeopleCert, 2023) — Plans practice
Practise all 12 Plans practice questions - start free → See the whole PRINCE2 7 Found. bank

Other PRINCE2 7 Found. areas

The same kind of free sample for every other section of the PRINCE2 7 Found. bank:

Key concepts of projects and PRINCE27 qThe PRINCE2 principles13 qPeople in successful projects17 qBusiness Case practice14 qOrganizing practice14 qQuality practice13 qRisk practice13 qIssues practice13 qProgress practice11 qThe PRINCE2 processes14 q

Study Plans practice with instant feedback

6 free questions · filter study mode by area and difficulty · error log with spaced repetition · no card, no dumps, no ads.

Create your free account →
Read next
PRINCE2 Foundation vs Practitioner: What Changes, What It Costs, Who Needs Which PRINCE2 Foundation (60 questions, closed book) vs Practitioner (scenarios, open book), both at 60% to pass. What each bundle costs and who needs which.
ExamDeck is an independent study tool, not affiliated with, endorsed by, or sponsored by PeopleCert. PRINCE2 7 Found. and related marks are trademarks of their respective owners, used for identification only. Exam facts checked against official PeopleCert materials (as of September 2026); always confirm current details with the vendor before booking.