PRINCE2 7 Found. · PeopleCert · Plans practice · Bank updated 2026-07-03
PRINCE2 7 Found. practice questions: Plans practice
5 free questions from 12 on this area · answer and explanation for each · no sign-up
These 5 questions come from the Plans practice section of our PRINCE2 7 Found. bank (12 questions on this area, which carries 8% of the real exam). Every question is original, with the correct answer explained and linked to the source it is drawn from.
1/5 · Plans practice
During a management stage, the project manager forecasts that the remaining work will exceed the stage tolerances agreed with the project board. Following PRINCE2 7 guidance on levels of plan, what should the project manager produce to cover the period to the end of the current stage (or project)?
AAn updated project plan covering only the benefits realisation period.
BA team plan detailing the remaining work packages for each team.
CA fresh stage plan for the next management stage, moved forward to start immediately.
DAn exception plan, to be approved by the next higher authority before it replaces the plan it supersedes.
Show answer & explanation
2/5 · Plans practice
Within the product-based planning technique, which management product is used to record a product's purpose, composition, derivation and quality criteria?
AConfiguration item record
BProduct breakdown structure
CProduct description
DProduct flow diagram
Show answer & explanation
3/5 · Plans practice · hard
Which statement about the project plan is correct according to PRINCE2 7?
AIt is produced by the team manager to schedule the work of a specific team.
BIt is replaced by the stage plan for the final management stage of the project.
CIt is mandatory, is developed during initiation, and gives the project board an overview statement of how and when the project's objectives are to be achieved.
DIt is optional and is only produced if the project board specifically requests a high-level overview of the work.
Show answer & explanation
4/5 · Plans practice · easy
Within the levels of plan described in the Plans practice, which plan is created specifically to regain control when a stage or project is forecast to exceed its agreed tolerances, and takes the place of the remaining portion of the plan it replaces?
AException plan
BStage plan
CProject plan
DTeam plan
Show answer & explanation
5/5 · Plans practice
During a planning workshop, a stakeholder insists that the product flow diagram for a project should display the resource allocated to each product and the calendar date each product is due, similar to a schedule. Which response best reflects the guidance on this diagram?
AThe product flow diagram must include resource names for each product but never shows dates
BThe product flow diagram is optional once a product breakdown structure exists, so its content is discretionary
CThe product flow diagram shows only the sequence in which products are to be delivered and the dependencies between them, not resources or dates
DThe product flow diagram replaces the schedule once the products have been sequenced
Show answer & explanation
Other PRINCE2 7 Found. areas
The same kind of free sample for every other section of the PRINCE2 7 Found. bank:
Study Plans practice with instant feedback
6 free questions · filter study mode by area and difficulty · error log with spaced repetition · no card, no dumps, no ads.
Create your free account →
ExamDeck is an independent study tool, not affiliated with, endorsed by, or sponsored by PeopleCert. PRINCE2 7 Found. and related marks are trademarks of their respective owners, used for identification only. Exam facts checked against official PeopleCert materials (as of September 2026); always confirm current details with the vendor before booking.