1/5 · Analysing and Managing Stakeholders · easy
When constructing a RACI chart to clarify roles for a set of business analysis tasks, what is the key rule regarding the 'Accountable' designation for any single task?
AThe Accountable entry can be left blank for low-risk tasks
BExactly one person or role should be Accountable for each task, even where several people are Responsible for doing the work
CThe Accountable person must personally perform most of the task's work
DMultiple people may share accountability for the same task as long as they agree among themselves
Show answer & explanation
B is correct. A RACI chart maps Responsible, Accountable, Consulted and Informed roles against tasks. Good practice, as taught in BCS business analysis materials, insists on a single Accountable owner per task so there is always one clear point of ownership, even though the work itself (Responsible) may be shared.
↗ the BCS Business Analysis Foundation syllabus v4.1 + 'Business Analysis, 4th Edition' (Paul & Cadle, BCS 2020) — Analysing and Managing Stakeholders
2/5 · Analysing and Managing Stakeholders
A finance director sponsors a change programme but delegates day-to-day oversight to a programme manager, attending only quarterly steering board meetings and rarely reading detailed status reports. The business analyst places this director in the high power/low interest quadrant of the power/interest grid. What is the recommended engagement approach?
AArrange weekly detailed working sessions matching the depth given to the programme manager
BExclude the director from communications entirely until the steering board meeting
CProvide concise, high-level information timed to key decision points, escalating promptly if the director's risk profile or interest changes
DCommunicate only via general newsletters, since the director's current power is not a concern
Show answer & explanation
C is correct. High power/low interest stakeholders are 'kept satisfied' — given sufficiently high-level, well-timed communication to retain their confidence without consuming their limited attention, while ensuring they are alerted quickly if their interest or the risk to the change increases.
↗ the BCS Business Analysis Foundation syllabus v4.1 + 'Business Analysis, 4th Edition' (Paul & Cadle, BCS 2020) — Analysing and Managing Stakeholders
3/5 · Analysing and Managing Stakeholders
An organisation extends the standard RACI chart to a RASCI chart for a complex requirements sign-off process. What does the additional 'S' represent, and how does it differ from 'Responsible'?
A'Sponsor' — the senior individual who funds the initiative and holds ultimate decision rights
B'Support' — provides resources, assistance or partial effort to the Responsible party, without owning delivery of the task
C'Stakeholder' — anyone with an interest in the task, equivalent to Informed
D'Signatory' — the person who formally signs off the deliverable, replacing Accountable
Show answer & explanation
B is correct. RASCI extends RACI by adding a Support role, capturing people who help the Responsible party carry out the task (for example, by supplying resources or effort) without themselves being accountable or solely responsible for the outcome. This distinguishes helpers from the person or people actually delivering the work.
↗ the BCS Business Analysis Foundation syllabus v4.1 + 'Business Analysis, 4th Edition' (Paul & Cadle, BCS 2020) — Analysing and Managing Stakeholders
4/5 · Analysing and Managing Stakeholders · hard
While building a RACI chart for a new supplier-onboarding process, a business analyst finds that six different managers have been marked as 'Consulted' for a single approval task, and no one has been marked 'Accountable'. What issue does this reveal, and what should the analyst recommend?
ALeave the chart as is but add a seventh manager as 'Informed' to ensure full transparency
BConvert all six 'Consulted' entries to 'Responsible', since consultation implies shared ownership of delivery
CThis is acceptable, since spreading consultation widely improves buy-in and RACI charts do not require an Accountable entry for every task
DAssign a single Accountable owner for the task and review whether all six 'Consulted' entries are genuinely needed, since excessive consultation can slow decisions while unclear accountability creates delivery risk
Show answer & explanation
D is correct. A well-constructed RACI chart avoids two common pitfalls: leaving a task without a named Accountable owner, and over-populating the Consulted role, both of which slow decision-making and blur ownership. The business analyst should ensure a single Accountable person is named and that consultation is limited to those whose input genuinely adds value.
↗ the BCS Business Analysis Foundation syllabus v4.1 + 'Business Analysis, 4th Edition' (Paul & Cadle, BCS 2020) — Analysing and Managing Stakeholders
5/5 · Analysing and Managing Stakeholders · easy
When plotting stakeholders on the power/interest matrix as part of stakeholder analysis, what does a stakeholder's 'interest' rating primarily represent?
AThe seniority of the stakeholder's job title relative to other stakeholders in the organisation.
BThe number of hours per week the stakeholder is contractually required to spend on project activities.
CThe size of the financial stake or monetary investment the stakeholder has committed to the project.
DThe degree of concern the stakeholder has about, and their expected level of involvement in, the outcome of the change.
Show answer & explanation
D is correct. In the power/interest matrix, 'interest' captures how concerned a stakeholder is about the change and how much they care about its outcome, which is distinct from their formal authority (power), financial exposure, or time commitment. Correctly separating these dimensions is essential to placing stakeholders in the right quadrant and choosing an appropriate engagement approach.
↗ the BCS Business Analysis Foundation syllabus — Analysing and Managing Stakeholders
Practise all 14 Analysing and Managing Stakeholders questions - start free → See the whole BCS BA Found. bank

Other BCS BA Found. areas

The same kind of free sample for every other section of the BCS BA Found. bank:

What is Business Analysis?9 qThe Competencies of a Business Analyst6 qThe Strategic Context for Business Analysis12 qThe Business Analysis Service Framework6 qInvestigating the Business Situation17 qImproving Business Services and Processes16 qDefining the Solution11 qMaking the Business Case9 qEstablishing the Requirements12 qDocumenting and Modelling Requirements13 qValidating and Managing Requirements6 qDelivering the Requirements7 qDelivering the Business Solution8 q

Study Analysing and Managing Stakeholders with instant feedback

6 free questions · filter study mode by area and difficulty · error log with spaced repetition · no card, no dumps, no ads.

Create your free account →
Read next
ECBA vs CCBA vs CBAP: Which IIBA Certification Fits Your Experience Level? (2026) ECBA, CCBA or CBAP? The eligibility gate that picks for you, what the 2026 ECBA rewrite changed, and each credential's three-year cost, verified against IIBA. PMI-PBA vs CBAP: The Business Analysis Certification Decision, Settled with Data PMI-PBA ($405-555, 36 months of experience) vs CBAP ($495-650 all-in, 7,500 hours plus references): eligibility, exam mechanics, three-year cost, salary data.
ExamDeck is an independent study tool, not affiliated with, endorsed by, or sponsored by BCS. BCS BA Found. and related marks are trademarks of their respective owners, used for identification only. Exam facts checked against official BCS materials (as of August 2026); always confirm current details with the vendor before booking.