HomeBCS BA Found.Practice questionsDelivering the Business Solution
BCS BA Found. · BCS · Delivering the Business Solution · Bank updated 2026-07-03

BCS BA Found. practice questions: Delivering the Business Solution

5 free questions from 8 on this area · answer and explanation for each · no sign-up

These 5 questions come from the Delivering the Business Solution section of our BCS BA Found. bank (8 questions on this area, which carries 5% of the real exam). Every question is original, with the correct answer explained and linked to the source it is drawn from.

Start 6 free in study mode → All BCS BA Found. sample questions
1/5 · Delivering the Business Solution · easy
Which statement best describes the business analyst's role during the design, development (build) and testing stages of a project, once the requirements have been signed off?
AThe BA supports design and build by clarifying and interpreting requirements for developers, and contributes to testing by helping define test cases and confirming that acceptance criteria have been met.
BThe BA's sole responsibility during these stages is to manage the project schedule and budget on behalf of the project manager.
CThe BA has no further involvement once requirements are signed off, since design, build and testing are purely technical activities for developers and testers.
DThe BA formally becomes the test manager for the duration of the project and takes full ownership of the test strategy.
Show answer & explanation
A is correct. The BCS syllabus emphasises that the BA's involvement does not end at requirements sign-off: the BA continues to support design and development by resolving ambiguities, and supports testing by helping ensure test cases trace back to requirements and acceptance criteria. This maintains a continuous thread from requirement to delivered solution.
↗ the BCS Business Analysis Foundation syllabus v4.1 + 'Business Analysis, 4th Edition' (Paul & Cadle, BCS 2020) — Delivering the Business Solution
2/5 · Delivering the Business Solution
A business analyst has been asked to assess an organisation's readiness for a planned restructuring by examining, alongside its stated strategy and structure, its shared values, management style, staff skills and staffing levels. Which technique is being applied?
APESTLE analysis.
BThe POPIT model.
CThe McKinsey 7S model.
DCPPOLDAT.
Show answer & explanation
C is correct. The McKinsey 7S model is used in the BCS approach to check organisational readiness by considering the 'hard' elements (Strategy, Structure, Systems) alongside the 'soft' elements (Shared values, Skills, Style, Staff), highlighting misalignments that could undermine a change. CPPOLDAT is a related but distinct readiness/scoping checklist focused on business dimensions such as customers, products and technology rather than organisational culture and behaviour.
↗ the BCS Business Analysis Foundation syllabus v4.1 + 'Business Analysis, 4th Edition' (Paul & Cadle, BCS 2020) — Delivering the Business Solution
3/5 · Delivering the Business Solution
The SARAH model is used by business analysts to help understand and manage how individuals typically respond emotionally to organisational change. Which sequence of stages does the model describe?
AShock, Denial, Anger, Bargaining, Acceptance.
BShock, Awareness, Resistance, Adaptation, Help.
CShock, Anger, Rejection, Acceptance, Help.
DSurprise, Avoidance, Resistance, Adjustment, Harmony.
Show answer & explanation
C is correct. The SARAH model (Shock, Anger, Rejection, Acceptance, Help) is used in BCS practice to help business analysts and change managers anticipate and support individuals as they move through predictable emotional reactions to change, rather than assuming a purely rational, immediate adoption of new ways of working. It is easily confused with the similar but distinct Kubler-Ross grief cycle.
↗ the BCS Business Analysis Foundation syllabus v4.1 + 'Business Analysis, 4th Edition' (Paul & Cadle, BCS 2020) — Delivering the Business Solution
4/5 · Delivering the Business Solution · hard
Six months after a new CRM system went live, the anticipated benefit of reduced customer-complaint handling time has not been achieved. Investigation shows the IT system was delivered on time and to specification, but the customer service team never adopted the revised complaint-handling process that was supposed to accompany it. Which technique, if used effectively during planning, would have most clearly shown that this process change was a necessary link between the IT enabler and the intended benefit?
AA benefits profile.
BA RASCI matrix.
CThe benefits dependency network.
DThe stakeholder wheel.
Show answer & explanation
C is correct. The benefits dependency network makes explicit the chain from an IT enabler, through the enabling changes and business (process/people) changes it requires, to the business benefits that ultimately depend on all of these being completed. In this scenario, the CRM system (IT enabler) alone could not deliver the benefit without the accompanying business change to the complaint-handling process, and the dependency network is designed precisely to surface such prerequisites during planning. A benefits profile records detail about an individual benefit but does not, by itself, expose these cross-dependencies.
↗ the BCS Business Analysis Foundation syllabus v4.1 + 'Business Analysis, 4th Edition' (Paul & Cadle, BCS 2020) — Delivering the Business Solution
5/5 · Delivering the Business Solution · hard
A stakeholder argues that user acceptance testing (UAT) is an unnecessary duplication because the development team has already completed system testing to confirm the solution works correctly against the technical specification. Which response correctly reflects the purpose of UAT?
AThe stakeholder is correct — UAT duplicates system testing, so it can reasonably be omitted once technical testing is complete.
BUAT is carried out by business users to confirm the solution meets their business needs and is fit for operational use, which technical testing alone cannot establish.
CUAT is only required when a direct changeover (Big Bang) implementation is used; phased and parallel implementations do not need it.
DUAT is simply a repeat of system testing carried out by an independent test team to provide a second technical sign-off before go-live.
Show answer & explanation
B is correct. The syllabus distinguishes technical testing stages (unit, integration, system testing), which verify that code meets its technical specification, from user acceptance testing, which is performed by business users to confirm the solution actually meets their business needs and is fit for operational use. The two are complementary, not duplicative, and UAT remains necessary regardless of implementation strategy.
↗ the BCS Business Analysis Foundation syllabus — Delivering the Business Solution
Practise all 8 Delivering the Business Solution questions - start free → See the whole BCS BA Found. bank

Other BCS BA Found. areas

The same kind of free sample for every other section of the BCS BA Found. bank:

What is Business Analysis?9 qThe Competencies of a Business Analyst6 qThe Strategic Context for Business Analysis12 qThe Business Analysis Service Framework6 qInvestigating the Business Situation17 qAnalysing and Managing Stakeholders14 qImproving Business Services and Processes16 qDefining the Solution11 qMaking the Business Case9 qEstablishing the Requirements12 qDocumenting and Modelling Requirements13 qValidating and Managing Requirements6 qDelivering the Requirements7 q

Study Delivering the Business Solution with instant feedback

6 free questions · filter study mode by area and difficulty · error log with spaced repetition · no card, no dumps, no ads.

Create your free account →
Read next
ECBA vs CCBA vs CBAP: Which IIBA Certification Fits Your Experience Level? (2026) ECBA, CCBA or CBAP? The eligibility gate that picks for you, what the 2026 ECBA rewrite changed, and each credential's three-year cost, verified against IIBA. PMI-PBA vs CBAP: The Business Analysis Certification Decision, Settled with Data PMI-PBA ($405-555, 36 months of experience) vs CBAP ($495-650 all-in, 7,500 hours plus references): eligibility, exam mechanics, three-year cost, salary data.
ExamDeck is an independent study tool, not affiliated with, endorsed by, or sponsored by BCS. BCS BA Found. and related marks are trademarks of their respective owners, used for identification only. Exam facts checked against official BCS materials (as of August 2026); always confirm current details with the vendor before booking.