PRINCE2 Agile Found. practice questions: Fix and Flex — the Hexagon
5 free questions from 29 on this area · answer and explanation for each · no sign-up
These 5 questions come from the Fix and Flex — the Hexagon section of our PRINCE2 Agile Found. bank (29 questions on this area, which carries 20% of the real exam). Every question is original, with the correct answer explained and linked to the source it is drawn from.
1/5 · Fix and Flex — the Hexagon · easy
According to PRINCE2 Agile's default fix-and-flex recommendation, which two of the six hexagon aspects should normally be fixed rather than flexed?
AScope and Quality
BQuality and Risk
CTime and Cost
DBenefits and Risk
Show answer & explanation
2/5 · Fix and Flex — the Hexagon
A Project Board is setting tolerances for a project that will use agile ways of working at delivery level. Which combination best reflects PRINCE2 Agile's recommended approach to tolerances across the hexagon?
AZero tolerance on all six aspects to guarantee complete predictability
BZero or very narrow time and cost tolerance, wider scope tolerance, with quality tolerance limited to flexing above an agreed minimum
CWide time and cost tolerance, with zero tolerance on scope and quality
DWide tolerance on benefits only, with every other aspect fixed at zero tolerance
Show answer & explanation
3/5 · Fix and Flex — the Hexagon · hard
Which statement about tolerance on the benefits aspect of the hexagon in an agile context is most accurate?
ABenefits tolerance cannot be set because agile projects do not maintain a Business Case
BBenefits tolerance replaces the need for time and cost tolerances in agile projects
CBenefits tolerance is always fixed at zero because benefits are only realised after project closure
DBenefits tolerance is set by the Project Board and can be protected by prioritising delivery of the highest-value features first via MoSCoW
Show answer & explanation
4/5 · Fix and Flex — the Hexagon
A delivery team is two days from the end of a fixed release time-box. It becomes clear that not everything originally planned can be finished without extending the time-box or increasing the budget. The requirements were previously prioritized with MoSCoW. What does PRINCE2 Agile recommend the team do?
ADeliver everything as originally planned by reducing the testing and quality checks applied to the 'must have' items
BReduce or drop the lowest-priority 'could have' items and, if still necessary, some 'should have' items, while ensuring all 'must have' requirements are still delivered to the agreed quality
CAsk the project board to extend the time-box slightly and increase the budget to cover the remaining work
DImmediately raise a formal exception to the project board, since any change to planned scope always requires re-baselining the project
Show answer & explanation
5/5 · Fix and Flex — the Hexagon
Which technique does PRINCE2 Agile pair with the Hexagon so that scope can be flexed in a controlled way while time and cost remain fixed?
AA RACI matrix
BMoSCoW prioritization (Must Have, Should Have, Could Have, Won't Have this time)
CEarned value management
DThe Kano model of customer satisfaction
Show answer & explanation
Other PRINCE2 Agile Found. areas
The same kind of free sample for every other section of the PRINCE2 Agile Found. bank:
Study Fix and Flex — the Hexagon with instant feedback
6 free questions · filter study mode by area and difficulty · error log with spaced repetition · no card, no dumps, no ads.
Create your free account →
ExamDeck is an independent study tool, not affiliated with, endorsed by, or sponsored by PeopleCert. PRINCE2 Agile Found. and related marks are trademarks of their respective owners, used for identification only. Exam facts checked against official PeopleCert materials (as of September 2026); always confirm current details with the vendor before booking.