1/5 · Focus Areas of Agile Delivery
A project team is prioritizing requirements using MoSCoW. According to PRINCE2 Agile guidance, what is a sensible upper limit for the proportion of total effort that 'Must Have' requirements should consume, in order to leave room for flexing scope?
AAs close to 100% as possible, to minimize project risk
BAround 60% of total effort, and it should not exceed roughly 80%
CExactly 50%, split evenly with Should Haves
D0%, because Must Haves should always be treated as Won't Haves
Show answer & explanation
2/5 · Focus Areas of Agile Delivery
During a sprint, a customer representative asks for a new feature to be added to the backlog after seeing an early increment. The team agrees it can be added, provided a lower-priority item of equivalent size is removed from the current scope. Which target is this behavior primarily demonstrating?
AEmbrace change
BProtect the level of quality
CKeep teams stable
DBe on time and hit deadlines
Show answer & explanation
3/5 · Focus Areas of Agile Delivery · easy
The INVEST mnemonic is commonly used within PRINCE2 Agile to assess the quality of a user story. What does the 'I' in INVEST stand for?
AImmediate
BIncremental
CIndependent
DIterative
Show answer & explanation
4/5 · Focus Areas of Agile Delivery
When applying MoSCoW to plan the effort within a delivery timeframe, PRINCE2 Agile suggests a guideline for the proportion of effort allocated to 'Must Have' requirements. Which statement best reflects this guideline?
AMust Have requirements should account for as close to 100% of the effort as possible, since anything left over is unlikely to be used.
BThe proportion of effort given to Must Haves is fixed by contract at project initiation and cannot be revisited once work begins.
CMust Have requirements should never exceed 10% of total effort, with the majority reserved for Won't Have items.
DAs a guide, Must Have requirements should account for no more than around 60% of the total effort, leaving room for some Should and Could Have requirements.
Show answer & explanation
5/5 · Focus Areas of Agile Delivery
A project's Agilometer assessment produces a very low score on the slider for 'ease of contact with the customer,' because the customer organisation is overseas across several time zones and rarely available. What should the project board conclude from this result?
AThe project should immediately increase the frequency of releases to compensate for the poor score.
BThe low score identifies a risk area needing specific management action, such as agreeing structured contact windows or a proxy customer, while agile ways of working can still be considered elsewhere.
CThe result should be disregarded because the Agilometer only applies to software development projects.
DAgile ways of working must be abandoned entirely for this project because the score is too low.
Show answer & explanation
B is correct. The Agilometer is designed to surface conditions that could make agile ways of working harder to apply, so that the project can plan mitigations rather than treat the score as a veto. A low score on ease of contact typically prompts actions like scheduling regular contact windows, appointing a customer proxy, or adjusting communication cadence. It does not mean agile cannot be used at all.
↗ the official PRINCE2 Agile Foundation Syllabus (PeopleCert) — Focus Areas of Agile Delivery
Other PRINCE2 Agile Found. areas
The same kind of free sample for every other section of the PRINCE2 Agile Found. bank:
Study Focus Areas of Agile Delivery with instant feedback
6 free questions · filter study mode by area and difficulty · error log with spaced repetition · no card, no dumps, no ads.
Create your free account →
ExamDeck is an independent study tool, not affiliated with, endorsed by, or sponsored by PeopleCert. PRINCE2 Agile Found. and related marks are trademarks of their respective owners, used for identification only. Exam facts checked against official PeopleCert materials (as of September 2026); always confirm current details with the vendor before booking.